Scaling BIM and Piloting Digital Twins: Driving Efficiency Across 1,000 Station Projects | Presentation

© 2025 Autodesk. All rights reserved.
Rail Summit 2025 Design & Make the Future of Rail
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 2
Gary Phillips BIM Specialist
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 3
• Railway Experience
• 10 Years as BIM-Modeller / -Coordinator / -Manager
• 5 Years BIM Specialist for DB
• DB past and current role
Agenda
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 4
01
02
03
The Statistics
The Company
The Past
04
05
06
The Present – Overview
The Present – Project Example
The Present – Lessons Learned
07 The Future – Digital Twin
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 5
The Statistics
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 6
33,000km Track
Copyright: Deutsche Bahn AG / Michael Neuhaus
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 7
5,400 Stations
Copyright: Deutsche Bahn AG / Christian Bedeschinski
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 8
5,400 Stations
Copyright: Deutsche Bahn AG / Christian BedeschinskiCopyright: Deutsche Bahn AG / Axel Hartmann Fotografie
8
2,500 Elevators
Copyright: Deutsche Bahn AG / Axel Hartmann Fotografie
10
5,300 Ticket Machines
Copyright: Deutsche Bahn AG / Christian Bedeschinski
10
9,300 Weather Shelters
Copyright: Deutsche Bahn AG / Axel Hartmann Fotografie
12
Over 12,000…
Clocks
Copyright: Deutsche Bahn AG / Pablo Castagnola
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 13
The Company
The Company
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 14
21,000 Employees
Long-Distance Regional Cargo InfraGO Energy Other
Rail Stations
42,000 Employees
29,000 Employees
68,000 Employees
2,000 Employees
62,000 Employees
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 15
The Past
The Past
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 16
Rail Summit 2022 Rail Summit 2023
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 17
The Present - Overview
The Present - Overview
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 18
The Present - Overview
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 19
The Present - Overview
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 20
The Present - Overview
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 21
The Present - Overview
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 22
The Present - Overview
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 23
The Present - Overview
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 24
The Present - Overview
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 25
Copyright: Deutsche Bahn AG / Axel Hartmann Fotografie
The Present - Overview
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 26
Copyright: Deutsche Bahn AG / Christian Bedeschinski
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 27
The Present – Project Example
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 27
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 29
The Present – Lessons Learned
Lessons Learned - Overview
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 30
Monitoring
Tools
Project Experience
Lessons Learned - Tools
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 31
Lessons Learned - Tools
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 32
Lessons Learned - Tools
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 33
Lessons Learned - Monitoring
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 34
• Data from CDE
• KPIs
• Targeted Communication
• Priorities - Past
• Priorities - Future
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 35
The Future
36
Copyright: Deutsche Bahn AG / Axel Hartmann Fotografie
Copyright: Deutsche Bahn AG / Pablo Castagnola
Copyright: Deutsche Bahn AG / Axel Hartmann Fotografie
The Future: Digital Twin Pilot
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 37
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 37
The Future: Digital Twin Pilot
The Future: Strategy
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025 39
„Von BIM zum digitalen Anlagenlebenszyklus“
“From BIM to the digital asset lifecycle“
Gary Phillips
DB InfraGO AG
Personenbahnhöfe
BIM Specialist
gary.phillips@deutschebahn.com
Thank you!
DB InfraGO AG | Construction Management | Gary Phillips | Autodesk Rail Summit | 04.11.2025
Slide 1 Slide 2 Slide 3 Slide 4 Slide 5 Slide 6 Slide 7: Agenda Slide 8: Agenda Slide 9: Agenda Slide 10: The Statistics Slide 11 Slide 12 Slide 13 Slide 14 Slide 15 Slide 16 Slide 17 Slide 18: The Company Slide 19: The Company Slide 20: The Past Slide 21: The Past Slide 22: The Present - Overview Slide 23: The Present - Overview Slide 24: The Present - Overview Slide 25: The Present - Overview Slide 26: The Present - Overview Slide 27: The Present - Overview Slide 28: The Present - Overview Slide 29: The Present - Overview Slide 30: The Present - Overview Slide 31: The Present - Overview Slide 32: The Present – Project Example Slide 33 Slide 34: The Present – Lessons Learned Slide 35: Lessons Learned - Overview Slide 36: Lessons Learned - Tools Slide 37: Lessons Learned - Tools Slide 38: Lessons Learned - Tools Slide 39: Lessons Learned - Monitoring Slide 40: The Future Slide 41 Slide 42: The Future: Digital Twin Pilot Slide 43: The Future: Digital Twin Pilot Slide 44: The Future: Strategy Slide 45