Qatar Rail - BIM Strategy and Mega Asset Data Management | Presentation
Download the full presentation now.

© 2024 Autodesk. All rights reserved.
Rail Summit 2024 Make the Future of Rail
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
MAKE THE FUTURE OF RAIL
© 2024 Autodesk. All rights reserved.
Albin Pjanic
Qatar Rail - BIM Strategy and Mega Asset Data Management
Fahad Al Jufairi
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
Agenda
1 Qatar Rail – Who Are We?
2 Doha Metro – Phase 1 BIM Implementation
3 Phase 1 – BIM Output
4 Transition to O&M
5 Qatar Rail – Future Plans
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Speakers
• Qatar Rail Company – Doha, Qatar
• Program Delivery Division
• Architect with 14+ years experience in AEC industry
Senior Building Information Management LeadAlbin Pjanic
• Qatar Rail Company – Doha, Qatar
• Service Delivery Division
• Engineer with 10+ years experience in Asset Management / O&M
Asset Management LeadFahad Al Jufairi
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
State Of Qatar
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
Qatar Rail
Who Are We?
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Doha Metro – Phase 1 The Program – A very tight schedule was successfully managed to enable delivery in time and to leading international standards,
much in advance of the FIFA FWC
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Doha Metro – Phase 1 The Program – A very tight schedule was successfully managed to enable delivery in time and to leading international standards,
much in advance of the FIFA FWC
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
A highly complex, world class Metro system delivered in a
very short time span through –
• An integrated delivery organization – Client →
Consultants → Contractors
• Robust Procurement, Construction, Testing and
Operations strategies
• Unwavering commitment to Safety, Environmental
impact, Corporate Social Responsibility,
Sustainability and Innovation
• To achieve an Efficient, Effective, Reliable,
Sustainable, Resilient & Flexible network and rail
service
Doha Metro – Phase 1
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Doha Metro – Phase 1
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Gold Line
15km Track
21min Al Azizyah to RBA
11 Stations
2014 Start
2020 Operation
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Red Line
42km Track
37min Lusail – Al Wakrah
18 Stations
2013 Start
2019 Operation
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Green Line
22km Track
24min Al Riffa to Al
Mansoura
11 Stations
2013 Start
2020 Operation
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Lusail Tram Network
25km Track
- Through Lusail
City
25 Stations
2013 Start
2022 Operation
4 Lines
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Qatar Rail – Metro Phase 1
BIM Implementation
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
BIM Mandate - ER
Set of BIM Guidelines and Standards
Collaboration Platform Mandate
Program Delivery BIM Implementation
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Employer’s Requirements
Design to be done in 3D Coordinated Environment (CDE)
All 2D drawings must be extracted from 3D models
Access to Contractors WIP and Shared Folders
4D/5D modeling required
Uniclass naming convention
BS1192 standards mandatory
Native modeling files + IFC must be delivered
BIM Mandate
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Qatar Rail BIM Guidelines
QRBG
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Set of BIM Standards documents
developed in collaboration with
Autodesk (QRBG)
QR BIM Guidelines issued for wide
implementation on Qatar Rail projects
Platform for internal collaboration implemented – Autodesk Vault
QRBG Qatar Rail BIM Guidelines
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Qatar Rail BIM Guidelines
Set of BIM Standards documents
developed in collaboration with
Autodesk (QRBG)
QR BIM Guidelines issued for wide
implementation on Qatar Rail projects
Platform for internal collaboration implemented – Autodesk Vault
QRBG
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Qatar Rail – Metro Phase 1
BIM Output
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Mega Asset data – Phase 1
6435 5500 299
Drawings and doc.
More than 1 million drawings, O&M manuals
etc.
BIM Models
More than 6000 Individial BIM models (ARCH, STR,
MEP, Systems)
Structured Data
COBie files, datasheets, etc.
Federated Models
299 WBS – combined models
1 mil
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
BIM Model Overview AB Station Model
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
BIM Model Overview AB Station Model
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Phase 1
9 different Design & Build contractors
PMC managing the design review
Qatar Rail monitoring design review
Use of BIM360 not mandated in the contract (contractors have their own collaboration platforms)
QR used BIM360Glue for model validation and review
Collaboration Platforms
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
AB Station Model
BIM Model Overview Powered by
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
AB Station Model
BIM Model Overview
Powered by
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Qatar Rail – Metro Phase 1
Transition to Operation and
Maintenance
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Standardization of the mandatory asset related information codes and the code description
Codification Principles
Approved Codes and Descriptions
Code Description Style Requirements
List of Maintainable Items
Space and Asset Naming [ Standardized Program wide through the Object Naming
AMCS – Asset Management Codification Standard
QR Codification
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Defines the information Level of Details (iLOD)
Provides D&B contractors with a method of exchanging information through BIM and COBie
Ensures consistent handover of information across all projects
Model Authoring Process
Identification of Master Attributes and Attribute Definition
iLOD Catalogue and Guidelines
QR Codification
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Construction Operations Building information exchange (COBie) addresses the handover of asset information between the D&B contractor and Qatar Rail.
The breakdown of models and COBie files follows the model file organization defined in the implementation plan.
The WBS codes used in file names, etc. follows the codes defined in the latest codification manual
Information Exchange – COBie
QR Codification
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Definition of delivery requirements to be completed for each model submission
Native authoring file format plus IFC and NWD files to be submitted
One COBie file per model
Cleaned and purged models
Model Delivery requirements
QR Codification
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Maintenance Management System MMS Implementation
Qatar Rail has selected IBM Maximo as its tool for
Enterprise Asset Management
o IBM Maximo is a leader in EAM
o Cost Effective solution
o Highly configurable to suite to every business
o Industry specific add-ons
Model Delivery requirements
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Asset Management Level of detail requirements
o Functional Locations
• Hierarchy
• Functionality/description
• System
o Assets
• Serial Number
• Manufacturer/Vendor
• Assemblies
o Items
• Manufacturer part number
• Specification
• Cost
Model Delivery requirements
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
BIM Interface in Maintenance
Applications of MMS
o Utilizing COBie for developing the asset registry: accurate and consistent asset data
o Analyzing the impacted location(s) of reported faults by examining the BIM model
o Planning and raising a CM Work Order: scheduling and assigning labor / resources
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
BIM Interface in Maintenance
Applications of MMS
o Utilizing COBie for developing the asset registry: accurate and consistent asset data
o Analyzing the impacted location(s) of reported faults by examining the BIM model
o Planning and raising a CM Work Order: scheduling and assigning labor / resources
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Qatar Rail – Metro Phase 1
Future Plans
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
• Transportation Master Plan Qatar 2050 (TMPQ 2050) envisages significant rail
infrastructure projects to be launched in future.
These projects will build Qatar’s national infrastructure, enable and develop a long -term
sustainable economy, and reduce carbon emissions for generations to come – leaving a
truly fitting and lasting legacy to His Highness as the original visionary of Qatar Rail.
Future of Qatar Rail
Qatar 2050قطر
للنقلالشاملةالخطة
Transportation Master Plan
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Future of Qatar Rail
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Lesson Learnt & Improvements Recommendation from Phase 1
40
Lesson Learnt (LL #25): ❑ Clashes and abortive work on
site from mistakes in the BIM models as different parties working
separately on older outdated models that had already been
revised i.e. Civil MEP and Systems clashes.
Recommended
Improvement:
❑ Investigate the use of a
Common Data Environment (CDE platform/tool) to share models between various project
teams and QR.
Based on model rework due to
changes in civils models and usage of outdated models – • Over 51 claims, costing millions of
DOLLARS • Quality of models was
questionable, and it required additional inhouse modeling
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Qatar Rail CDE
System Integrator
CDE Setup ▪ Project folder setup
▪ Phase 1 available info
▪ RVT Families Library
▪ RVT and NWC template
▪ QR BIM Requirements
▪ Example model
PMC Red Line
PMC Blue Line
PMC Gold Line
PMC Green Line
D&B Contractor Red
D&B Contractor
Blue
D&B Contractor
Green
D&B Contractor Gold Possible System
Interfaces
Possible Bridge Connection to Contractors External CDE
GIS
MMS
Aconex
D&B Contracto
r 1
D&B Contracto
r 2
Other External
Contributor s
• BIM Requirements for Design
• BIM Requirements for Construction
ACC Implementation Proposal Concept
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Qatar Rail requirements alignment with ISO 19650
Information Container Identification
Approval WorkflowsTransition of Containers
ClassificationSuitability StatusRevision Control
Permission Based AccessManaged ProcessEstablish Common Platform
RFI TrackingIssue Tracking
Model Federation
Project InsightMobile Access
Design Change Management
File Viewing CapabilitiesDesign Tool Integration
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24 Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
RA IL SUMMI T 20 24
Accomplishing a Vision
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
Q&A
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
MAKE THE FUTURE OF RAIL
https://www.qr.com.qa
Albin Pjanic
apjanic@qr.com.qa
Senior BIM Lead
https://www.qr.com.qa
Fahad Al Jufairi
faljufairi@qr.com.qa
Asset Management Lead
Data Classification: C1 – INTERNAL. Do not distribute outside of the organization.
Rail Summit 2024 Presentation Folie 1: Rail Summit 2024 Folie 2: Qatar Rail - BIM Strategy and Mega Asset Data Management Folie 3: Agenda Folie 4: Speakers Folie 5: State Of Qatar Folie 6: Qatar Rail Folie 7: Doha Metro – Phase 1 Folie 8: Doha Metro – Phase 1 Folie 9: Doha Metro – Phase 1 Folie 10: Doha Metro – Phase 1 Folie 11: Gold Line Folie 12: Red Line Folie 13: Green Line Folie 14: Lusail Tram Network Folie 15: Qatar Rail – Metro Phase 1 Folie 16: Program Delivery BIM Implementation Folie 17: BIM Mandate Folie 18: QRBG Folie 19: QRBG Folie 20: QRBG Folie 21: Qatar Rail – Metro Phase 1 Folie 22: Mega Asset data – Phase 1 Folie 23: BIM Model Overview Folie 24: BIM Model Overview Folie 25: Collaboration Platforms Folie 26: BIM Model Overview Folie 27: BIM Model Overview Folie 28: Qatar Rail – Metro Phase 1 Folie 29: QR Codification Folie 30: QR Codification Folie 31: QR Codification Folie 32: QR Codification Folie 33: Maintenance Management System Folie 34: Asset Management Folie 35: Applications of MMS Folie 36: Applications of MMS Folie 37: Qatar Rail – Metro Phase 1 Folie 38: Future of Qatar Rail Folie 39: Future of Qatar Rail Folie 40: Lesson Learnt & Improvements Recommendation from Phase 1 Folie 41: ACC Implementation Proposal Concept Folie 42: Qatar Rail requirements alignment with ISO 19650 Folie 43 Folie 44: Accomplishing a Vision Folie 45: Q&A Folie 46