MADRID-ATOCHA RAILWAY COMPLEX: DIGITAL CONSTRUCTION COORDINATION
AGENDA Context of the Railway Complex
Collaborative BIM Strategy
Construction Monitoring and Control
Ongoing Activities
Key Takeaways
1
2
3
4
5
ATOCHA DIGITAL
Team speakers
3
Adrián García Rodríguez
BIM Manager
Technical Assistance for Coordination and Control at Atocha Digital
Samuel J. Triana González
BIM & VDC Expert
Technical Assistance for Coordination and Control at Atocha Digital
ATOCHA DIGITAL
INECO | SUSTAINABLE MOBILITY AND DIGITAL TRANSFORMATION ENGINEERING AND CONSULTANCY
4
Developed 12,000 km of high-speed rail
Involved Aena’s airport network development
Leading role in ERTMS deployment (Europe)
One of Spain’s largest architectural firms
First Spanish firm ICAO- certified for flight procedure design
Over 50 in-house digitalization solutions
Major IT provider for the
Spanish Administration
Improving rail intelligence and ports for 22 authorities
Digitalizing the sector to support State Roads Demarcations
110% revenue growth in 2024 over 2022 on resilience and climate change
Committed to client co- creation for innovation
10+ years of AI application and 15+ pilot projects IN ALL
continents
+300 disciplinesTurnover
+440 M€+6,000 professionals
+55 years of experience
ATOCHA DIGITAL
Image courtesy of [GOOGLE]
PHASE 1: (finished)
Puerta de Atocha Station
PHASE 2: (ongoing)
High-Speed Through Station Historic Building refurbishment Carlos V Access redesign
Facility Services Building
PHASE 3: (on hold)
High-Speed and Commuter Halls
PHASE 4: (in progress)
Civic Square and Parking
In 2008, an Informative Study was published that planned the future development of the Railway Complex,
organizing it into 4 phases.
5
[1] CONTEXT OF THE RAILWAY COMPLEX | PHASED APPROACH
ATOCHA DIGITAL 6
Standard Gauge Tracks Iberian Gauge Tracks Buildings Urban Planning Other Works
Some financed by the EUROPEAN INVESTMENT BANK and NEXT GENERATION EU
STRATEGIC IMPORTANCE in the development of the transport and rail network, locally and nationally.
OVERLAPPING WORKS IN TIME AND SPACE maintaining the station's functionality
HIGH NUMBER of INVOLVED PARTIES
Multiple Project SCOPES at
different stages of BIM MATURITY
AFFECTED SERVICES on the railway, architectural and adjacent infrastructure areas.
[1] CONTEXT OF THE RAILWAY COMPLEX | OVERVIEW KEY POINTS
ATOCHA ALMUDENA GRANDES
STATION
REINA SOFÍA MUSEUM
THYSSEN MUSEUM
PRADO MUSEUM
“ L R TIRO” RK
ROYAL BOTANICAL GARDEN
CHAMARTÍN CLARA CAMPOAMOR
STATION
ATOCHA DIGITAL 7
[2] COLLABORATIVE BIM STRATEGY | ATOCHA IN FIGURES
+6.500.000 Construction BIM
data
+180.000 BIM instances organized
into 115 element classes
+150 Models coordinated by the
Technical Coordination Assistance
9 Technical Specialties
34 Disciplines 110 Sub-disciplines
+150 Types of technical and BIM
documents
+50 Types of review and approval
workflows
+500 agents involved in the
construction works
76 Areas affected and unaffected,
within the complex
+11.500 documents uploaded to
the CDE
+490 GB of data stored in the
CDE
ATOCHA DIGITAL
Coordination with the Contract CDE of each project
Workflows and Folder Structure in the CDE
BIM MODEL PROVIDER 1
ATOCHA DIGITAL
BIM MODEL PROVIDER 2
BIM MODEL PROVIDER 3
BIM MODEL PROVIDER N
8
[2] COLLABORATIVE BIM STRATEGY | CENTRALIZATION & WORKFLOWS
• Exchange information between asset projects
• Record, Review and control documentation
• Centralized and standardized source of info
BMP 2
BMP 6
BMP 3
BMP 1
BMP 4
BMP 5
BMP 7
BMP N
ATOCHA DIGITAL
Atocha Digital – CDE Objectives
BMP : BIM Model Provider
PUBLISHED
SHARED
INTERVENTION N
INTERVENTION 3
INTERVENTION 2
INTERVENTION 1
/02-ACTU
/01-PEYC
REFERENCE AND START-UP DOCUMENTATION
/03-COO
INTEGRATED CONSTRUCTION MODEL
INTERVENTION N
INTERVENTION 3
INTERVENTION 2
INTERVENTION 1
/02-ACTU
Validation by ADIF and TCA
ATOCHA DIGITAL
General Standards: Nomenclature, Best practices, Segregation and Integration
Information Needed: Attribute matrix, Attribute values, Classification system
Procedures: Atocha Coordination Strategy, Information Workflows, Exchange
Software Templates: Shared Parameters, IFC Export, Psets, Automations
Shared Resources: CADs, Point Clouds, Shared coordinates models
Docs Templates: Aligned PEB, Quality control, Meetings, Clash matrix
[2] COLLABORATIVE BIM STRATEGY | ATOCHA COORDINATION RESOURCES
9
ATOCHA DIGITAL 10
[2] COLLABORATIVE BIM STRATEGY | DIGITAL ENVIRONMENT
COMMON DATA ENVIRONMENT
MODEL AUTHORSHIP
PROGRAMMING & AUTOMATION
COORDINATION
REFERENCE DATA
ONGOING INITIATIVES
VISUALIZATION
BIM-GIS
PRE-DESIGN
ATOCHA DIGITAL 11
[2] COLLABORATIVE BIM STRATEGY | INTEGRATED MODEL
+603 Level
High-Speed Through Station (underground):
• Platforms and tracks • Tunnels
+615 Level
• P3A&P3B Parking
• Commuter rail infrastructure
• Méndez Álvaro Street
+620 Level
• Carlos V Access redesign
• Historic Building refurbishment
• Existing Puerta de Atocha Station
• High-Speed Through Station
+662 Level
• Historic Building Roof
• Commuter Rail Roof / P2 Parking
• Puerta de Atocha Station Roof
• High-Speed Through Station Roof
HIGH NUMBER of INVOLVED PARTIES
P.S.M
STANDARD GAUGE TRACKS
031-AVACMSC 040-PASD.D.C.I.
090-ACM
BUILDING
120-TVP
BUILDING
100-PP3
BUILDING
070- ITE
BUILDING
200-CLI
BUILDING
STANDARD GAUGE TRACKS
060-AVA
STANDARD GAUGE TRACKS
061-442CMS
IBERIAN GAUGE TRACKS
D.D. Superstr. Projects
STANDARD GAUGE TRACKS
020- LAV
D.D.C.C.S.
D.D.S.G. 080-CTA
BUILDING
STANDARD GAUGE TRACKS
010-ISS D.D.F
STANDARD GAUGE TRACKS
051- CRNCMS
D.D.C.C.S.
D.D. High-
Speed. R.S.P.
140-SER
BUILDING
D.D.E130-SET
BUILDING
032-AVACMSV D.D.C.C.S
STANDARD GAUGE TRACKS
050-CRN
T.D. High-
Speed. R.S.P.
STANDARD GAUGE TRACKS
220-NAV D.D.
Stations Center
BUILDING
IBERIAN GAUGE TRACKS
060-442M.D.
ATOCHA DIGITAL
[3] CONSTRUCTION MONITORING & CONTROL | MODEL EXCHANGE & COORDINATION
Image courtesy of [Name]
COMUNICACIÓN
DESIGN COLLABORATION
PROJECT TIMELINE
SHARE PACKAGES
CONSUME PACKAGES
UPDATED VERSIONS PROJECT VIEWER
PP3
AVA
442
ACM
TVP
PAS
MODEL COORDINATION
INTEGRATED CONSTRUCTION MODEL
MULTIPLE COORDINATION SPACES
12
ATOCHA DIGITAL
AUTODESK CONSTRUCTION CLOUD
13
Image courtesy of [Name]
NAVISWORKS MANAGE
[3] CONSTRUCTION MONITORING & CONTROL | ISSUE SYNCHRONIZATION
ATOCHA DIGITAL 14
Resolving Temporary Conflicts TEMPORARY WORK AREA (TWA)
Ticket Sales and Police Station
TBI Historic Building
Implementation of the 4+4+2 Scheme
Carlos V Access and Historic Building
Carlos V Acces and Historic Building
Ticket Sales and Police Station
Implementation of the 4+4+2 Scheme
RENFE premises
TWA Available
Detected Clash between TWA (PROJECT information)
The Available Spaces and necessary surface areas for
each project are studied.
New distribution of TWA proposed in accordance
with construction planning
[3] CONSTRUCTION MONITORING & CONTROL | CLASH DETECTION
ATOCHA DIGITAL 15
[3] CONSTRUCTION MONITORING & CONTROL |DATA STANDARDIZATION
IfcRail.RAIL IfcPile.SUPPORT
IfcWall.RETAININGWALL
IfcTransportElement.ESCALATOR
IfcColumn.COLUMN
IfcRailing.BALUSTRADE
IfcStair.STRAIGHT_RUN_STAIR
IfcBeam.BEAM IfcSlab.SIDEWALK
IfcSign.USERDEFINED
IfcTrackSlab.BASESLAB
IfcRailwayPlatform.PASSENGER
IfcRoof.SHED_ROOF
IfcPipeSegment.RIGIDSEGMENT
IfcDuctSegment.RIGIDSEGMENT
IFC CLASSES & TYPES
FUN.VIA.010.010
Carril FUN.EST.020.020
Pilote de cimentación
FUN.EST.030.010
Muro de contención
FUN.ARQ.050.010
Escalera mecánica
FUN.EST.050.010
Pilar
FUN.ARQ.020.250
Barandilla
FUN.EST.050.040
Escalera de estructura
FUN.EST.060.040
Viga
FUN.VIO.020.020
Acera
FUN.SEN.010.010
Señal mecánica
FUN.VIA.060.010
Vía en placa
FUN.VIA.060.030
Losa de hormigón
FUN.ARQ.010.110
Cubierta prefabricada
FUN.ISA.040.020
Tubería saneamiento
FUN.IVE.030.010
Conducto
FUNCTIONS - SCFCLASS RIH V02
SUV_CRR_Carril_
UIC60 EST_CPF_PiloteCiment_
0,8m_HA-35
EST_EEV_MurContencion_
0,7m_HA-35
ARQ_AMC_EscalerMecanica_
L01_001
EST_EEV_Pilar_Circular_
0,8m_A.LAM.S335JR
ARQ_CAI_Barandilla_
Pasamano_A.INOX_40
EST_EEV_EscaleraEstructura_
Zanc.Met_Forj.Mixt_15cm
EST_EEH_Viga_
IPE-400_A.LAM.S335JR
URB_CPU_PavimentoPeatonal_
10cmM.CEM
CMS_SÑL_SeñalMecanica_
TipoIIA
SUV_VIP_ViaPlaca_
0,25m_HA-30
EST_EEV_ForjadoHormigon_
0,3m_HA-30
ARQ_ENV_SistEspecCubiert_
15cm
ISA_CVL_TuberiaSaneamiento_
SistemaFecales_PVC
IME_EDV_Conducto_
SistemaVentilacion_30x60cm
NAMING CONVENTION
1. IFC STANDARD 2. CLASSIFICATION SYSTEM 3. NAMING CONVENTION
ATOCHA DIGITAL 16
CHECKLIST
VISUAL REVIEWS
[3] CONSTRUCTION MONITORING & CONTROL | QUALITY ASSURANCE & QUALITY CONTROL
Empty data
IFC DATA VALIDATION
AUTODESK MODEL CHECKER INFORMATION DELIVERY SPECIFICATION (IDS)
PROJ01: TEMPORARY PARKING PROJ02: PASSING STATION PROJ01: TEMPORARY PARKING PROJ02: HIGH-SPEED THROUGH STATION
ATOCHA DIGITALPROJ04: HISTORIC BUILDING
PROJ03: TICKET OFFICE
PROJ05: TRACKS 0A AND 0B
157
54 103
CLASSIFICATION SYSTEM IFC DEFINITIONS ADIF OBJECT DATA
ADIF PROJECT DATAGLOBAL DASHBOARDFILES & METADATA
ATOCHA DIGITAL 17
VISUAL PROGRAMMING
TEXTUAL PROGRAMMING
• Generation of Attributes in BIM Models
• Fil ling Attribute Values from External Sources
• Configuration of Complex Geometries
• Data Quality Reviews
• Model and Information Exports/ Imports
TYPES OF AUTOMATIONS
[3] CONSTRUCTION MONITORING & CONTROL | BIM PROCESS AUTOMATION
ATOCHA DIGITAL
FORMS PHOTOS ACTIVITIES
DASHBOARDS
ISSUES
SHEETS
18
[3] CONSTRUCTION MONITORING & CONTROL | TOOLS, LINKS & DATA
FORMSACTIVITIESDASHBOARDSISSUESCONSTRUCTION PHOTOSSHEETS
ATOCHA DIGITAL 19
[4] ONGOING ACTIVITIES | VISUALIZATION & SIMULATION
ATOCHA DIGITAL 20
[4] ONGOING ACTIVITIES | BIM-GIS INTEGRATION
ATOCHA DIGITAL 21
[4] ONGOING ACTIVITIES | DIGITAL TWIN | TANDEM
ATOCHA DIGITAL 22
Mixed RealityAugmented and Immersive Reality
[4] ONGOING ACTIVITIES | VIRTUAL REALITY | WORKSHOP XR
ATOCHA DIGITAL 23
[5] KEY TAKEAWAYS | OUTCOMES & NEXT STEPS
LESSON LEARNED
• Ensure stakeholders understand the
value of BIM and digital environments
from the start
• Early planning of tasks and phase-specific
requirements is essential
• Providing shared resources and dashboards
accelerates workflows and monitoring
• Standardize processes wherever possible
without overcomplicating
BENEFITS ACHIEVED
• Time savings in production and consistency in
documentation
• Early detection of errors and support in
generating quality deliverables
• Improved communication between agents,
reducing issues
• Fast access to up-to-date information and
delivery of a valuable digital asset for
operations
FUTURE CHALLENGES
• Avoid BIM being perceived as merely a set
of deliverables
• Keep models up-to-date and periodically
coordinated despite software limitations
• Prevent information loss between native
and OpenBIM models
• Maintain detailed and up-to-date
construction schedules aligned with ongoing
works
Only through careful coordination can multiple projects coexist in harmony within the same
space and time, turning complexity into opportunity…
Autodesk and the Autodesk logo are registered trademarks or trademarks of Autodesk, Inc., and/or its subsidiaries and/or affiliates in the USA and/or other countries. All other brand names, product names, or trademarks belong to their respective holders. Autodesk reserves the right to alter product and services offerings, and specifications and pricing at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document. © 2025 Autodesk. All rights reserved.
Slide 1 Slide 2: AGENDA Slide 3: Team speakers Slide 4: INECO | SUSTAINABLE MOBILITY AND DIGITAL TRANSFORMATION ENGINEERING AND CONSULTANCY Slide 5 Slide 6 Slide 7 Slide 8 Slide 9 Slide 10 Slide 11 Slide 12 Slide 13 Slide 14 Slide 15 Slide 16 Slide 17 Slide 18 Slide 19 Slide 20 Slide 21 Slide 22 Slide 23 Slide 24