Large-Scale Railway Projects: Planning and Coordination Strategies

Lorena Franqueira Losada Civil Engineer/Adif

2

Large-Scale Railway Projects: Planning and Coordination Strategies

In recent years, even before the BIM Plan came into force in public procurement, Adif has

been a pioneering organization in committing to BIM implementation for all future projects. According to this, Chamartín and Atocha Digital are initiatives developed under a strategic framework aimed at promoting the digitalization of all its future developments through BIM

methodology. These unique, complex, and ever-changing interventions represent a major challenge that requires a shared, coordinated, and federated vision, supported by Technical

Coordination Assistance. This approach will help to get a digital twin in the future, enabling advanced asset management and data-driven decision-making.

Image courtesy of [Name]

Large-Scale Railway Projects :

Planning and Coordination Strategies

01

02

03

04

05

BIM Implementation in Adif

BIM Documentation Ecosystem in Adif

TCA to coordinate large-scale railway projects

BIM Framework Plan: Coordination requirements

Large Scale Projects: Chamartin and Atocha

4

BIM implementation in Adif

2016-2017 2018-2019 2020-2021 2022-2023 2024-2025

❑ Interdisciplinary

study phase begins

by defining the

roadmap

❑ Definition of the

scope of BIM

objectives

❑ Defined information

requirements for early

procurement.

❑ First BIM Committee

established

❑ First procurement process

for developing the BIM

documentation framework

❑ More than 20 projects are

initiated using BIM

❑ Over 400 employees trained

across the organization.

❑ BIM Technical Office

established and BIM

included as a strategic

initiative.

❑ Development of

BIM

implementation

standard for

projects and

construction.

❑ Mandatory use of

CDE for all

projects and

works

❑ Improvement of all

BIM documentation

❑ Development of

additional model

uses for Operation

and Maintenance

> 5.538.000 €

< 5.538.000 €

> 2.000.000 €

BIM Plan - Public Procurement

UNE-EN ISO 9000 CAD CDE BIM

CDEPMB BIM

BIM Level of Development

MEDIUM (October 2025)

INITIAL (April 2024)

Economic threshold for

projects and works.

CDE PMB

BIM

BIM LIBRARY BIM TRAINING

BIM Level of Development

ADVANCED (October 2025)

MEDIUM (January 2023)

WORKING TO ACHIEVE AN

ADVANCED LEVEL

M ODEL USES F OR:

BIM Plan -

ASSET FOR OPERAT ION AND

M AINT ENANCE3D

4D

5D

5

BIM Documentation Ecosystem in Adif

BIM

STRATEGY

PEOPLE PROCESSES

BIM REQUIRE MENTS

ICT

BIM STANDARD

BIM implementation strategy integrated

into the Organization’s processes

INTEGRATION OF THE BIM METHODOLOGY IN ADIF

DEVELOPMENT AND MANAGEMENT OF THE

BIM METHODOLOGY

DOCUMENT APPROVAL PROCESS

DEVELOPMENT OF THE BIM STANDARD

MODEL USES IN BIM IMPLEMENTATION

BIM METHODOLOGY APPLIED TO

CONSTRUCTION WORKS

REVIEW AND VALIDATION OF BIM DELIVERABLES

USE OF THE COMMON ENVIRONMENT (CDE)

BIM METHODOLOGY APPLIED TO

PROJECTS

ADIF AND ADIF AV BIM MANUAL

BIM ROLES

Adif / Adif-AV PROVEEDOR

Contract

Manager Information

Manager

BIM

Manager

BIM

Supervisor

Project/

Construction

Manager

Information

Manager

BIM

Manager

BIM

Modeler

BIM

Coordinator

BIM REQUIREMENTS TO INCLUDE IN TENDERS

BIM REQUIREM ENTS

UNIQUE BIM SCOPE

TYPE 1

TYPE 2

TYPE 3

TYPE 4

TYPE 5

o Mandatory Use of CDE o Information

Management Plan

o Use of CDE o Navigation and model

query

o Use of CDE o Models review

o Use of CDE o Models maintenance

o Use of CDE o Models creation

o BIM Clauses.

BIM REQUIREM ENTS

TYPE 3+5

o Use of CDE o Models

review

o Models creation

COMBINATION OF

BIM SCOPE

ADIF has chosen Autodesk Construction Cloud

(ACC) as its Common Data Environment (CDE)

for managing information related to their projects.

BIM DOCUMENTS

CDE GUIDE

E

CDE USAGE GUIDES

SUP GUIDE

GUIDES FOR SUPPLIERS

SPE GUIDE

SPECIFIC GUIDES

STYLE GUIDE

STYLE GUIDE MANUALS STYLE GUIDE TEMPLATES

LEVEL OF

DEVELOP

MENT

(LOD)

LEVEL OF

INFORMA

TION

(LOI)

QUALITY ASSET FOR THE

ENTIRE LIFECYCLE

LEVEL OF INFORMATION NEED

(LOIN)

MAJOR INTERVENTION

6

TCA to coordinate large-scale railway projects

ADIF COORDINATES MAJOR RAILWAY TRANSFORMATION PROJECTS USING BIM METHODOLOGY

INTERVENTION 01

INTERVENTION 03

INTERVENTION 05

INTERVENTION 06

TSD – TCA ATOCHA (2023)

-Mandatory use of a CDE (January 2023)

BIM premises prior to : - -BIM Plan in public procurement (April 2024)

TSD – TCA CHAMARTÍN (2021)

BIM premises prior to: -Mandatory use of a CDE (January 2023) -BIM Plan in public procurement (April 2024)

DEPUTY DIRECTORATE

FOR MAJOR PROJECTS

COORDINATION

DACGP

• Manage procedures with various authorities and developers • Coordinate projects and works taking place in the same location and timeframe • Identify issues through an overall overview of all activities

• Ensure the proper transition from the design phase to the construction phase

Technical and BIM Team º

TCA

Technical Team

• Compatibility analysis • Coordination and monitoring • Risk identification

• Proposal of solutions

BIM Team

• Writing manuals and guides • Model analysis • Federated Model

• 3D and 4D Coordination

Support Team

• Execution of on-demand work according to deliverable requirement

CONSULTANCY AND TECHNICAL

ASSISTANCE FOR THE COORDINATION

AND CONTROL OF WORKS

INTERVENTION 04

INTERVENTION 02 INTERVENTION 07

7

BIM Framework Plan: Coordination requirements

COMMON GUIDELINES IN BIM METHODOLOGY FOR ALL AGENTS

BIM clauses as an Annex to the TCA contract

BIM TO ASSIST WITH THE COORDINATION

CHALLENGE BIM

FRAMEWORK

PLAN

o Understand the current status and existing elements

o Visualize different projects together

o Simulate construction phases of the projects

o Detection of issues before they occur on site

o Gather information for operation and maintenance

BIM TO PROMOTE A COLLABORATIVE SPACE

MODEL AWARDEE (MA) = BIM MODEL PROVIDER THAT WILL PARTICIPATE IN:

PROJECT PHASE

BIM Works

BIM Clauses

DESIGNER

CONSTRUCTION PHASE

BIM Clauses

TACONTRACTOR

BIM Works BIM Supervision

BIM M. Adif TCA/Adif

BIM OBJECTIVES

Model for the life cycle

Decision-making

Quality

Coordination

Project control

Risk mitigation

BIM monitoring

Current status

Operational economics

Information consistency

Adif Asset Management

Comunication

MODEL USES

Authoring with 3D BIM Models

(GE 013)

Document management, collaboration,

and BIM Delivery (CO 011)

2D Documentation, Drawings

(CO 022)

Visualization for commercial and

institutional purposes (CO 053)

Digital meetings (CO 043)

BIM Coordination (3D), clashes or

interference (AN 023)

Construction Simulation (4D)

(AN 034)

Railway interoperability (AN 089)

Digital Mapping of Existing Assets

(RE 013)

(AN) ANALYZE

(CO) COMMUNICATE

(GE) GENERATE

(RE) COLLECT

BIM DOCUMENTATION TO ENSURE COORDINATION

ALIGNED TEMPLATE for BEP (TCA-MA)

DOC TEM

REF DOC

BASE DOCUMENTS PROTOTYPE MODEL SHARED COORDINATES WORK STANDARS

TCA

WORK TEMPLATES

SOFT TEM

REVIT TEMPLATES ISTRAM TEMPLATES

AUTOCAD TEMPLATES

ZON SCO

SCOPE ZONING

OBJECTIVE:

o The MA is part of a mayor intervention

o Guiding the MA at the beginning of the work

o Establishing guidelines for consistency

8

Large Scale Projects: Chamartín and Atocha Digital BIM DELIVERABLES

Project model

PROJECT PHASE

Current state model

BIM Execution Plan

for project

CONSTRUCTION PHASE

BIM Execution Plan

for construction

Project model audit

Initial construction

model

Construction

monitoring model

As-Built model

1) They must have the same:

o LEVEL OF DEVELOPMENT (LOD)

o LEVEL OF INFORMATION (LOI)

o COORDINATE SYSTEM

2) They must be useful to identify clashes

between interventions during the design

phase and the construction phase

VS INTERVENTION B

INTERVENTION A

CHAMARTÍN DIGITAL

ATOCHA DIGITAL

Adif Psets

Atributes allow consistency

in information

BIM IN GLOBAL COORDINATION

3) They must become future digital twins

BIM MODELS

OBJETIVE : TO BE INCLUDED INTO AN

INTEGRATED MODEL

OBJETIVE : TO AVOID MISTAKES AND

SAVE COSTS

OBJETIVE : TO BE A LIVING ASSET AFTER

CONSTRUCTION

© 2025 Autodesk. All rights reserved.

Thank you!

Slide 1 Slide 2: Large-Scale Railway Projects: Slide 3 Slide 4: BIM implementation in Adif Slide 5: BIM Documentation Ecosystem in Adif Slide 6: TCA to coordinate large-scale railway projects Slide 7: BIM Framework Plan: Coordination requirements Slide 8: Large Scale Projects: Chamartín and Atocha Digital Slide 9