INNOVATIVE SLAB

TRACK SOLUTIONS

MARIUSZ KALINOWSKI

STEFAN VONBUN

INNOVATIVE SLAB TRACK SOLUTIONS RHOMBERG SERSA RAIL GROUP

MARIUSZ KALINOWSKI

STEFAN VONBUN

Rail Summit 2024

Copenhagen, Denmark

DO YOU REMEMBER?

DO YOU REMEMBER?

DO YOU REMEMBER?

6

SLAB TRACK DEVELOPMENTS

60 YEARS OF INVENTIONS TO INCREASE AVAILABILITY AND REDUCE MAINTENANCE

Autodesk Rail Summit 2024

DECADES OF SEAMLESS

SLAB TRACK PROJECTS

Project Application System 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Cologne/D •

Lötschberg/CH •

Ingolstadt/DE •

Monterey/MX -

Brenner/AT •

Malmö/SE •

Zurich/CH •

Heitersbergtunnel/CH •

GZU/AT •

Hohenturm/DE •

CEVA/CH •

Ulm – Wendlingen/DE •

Copenhagen/DK •

Stuttgart 21 Lot B/D/DE •

Koralmtunnel/AT •

• Rheda • LVT • Porr

High-speed (HS) Partial HS Tunnel Metro

Autodesk Rail Summit Copenhagen 2024

Rhomberg Sersa Rail Group | Worldwide

CONSTRUCTION, RECONSTRUCTION AND MAINTENANCE

OF RAILWAY INFRASTRUCTURE

OPERATION AND MAINTENANCE OF RAIL-BOUND

VEHICLES

700 Million Euros

revenue

3,000 Employees

> 230 Rail-bound vehicles

1

2

3 4

67 95

8

3 CONTINENTS

9 MARKETS

100 BRANCHES

WORLDWIDE

North America

Canada

USA

Europe

Switzerland UK1

2

3

4

5 Germany

Austria Ireland

9

6

7

Australia

Project business: selected locations worldwide

Nordics 8

© Metroselskabet og Hovedhadens Letbane

© Deutsche Bahn © World Travel Images

© Rhomberg Sersa Rail Group

HIGH FIXITY // SLAB TRACK SYSTEMS

MAIN CATEGORIES

Monolithic (e.g. Rheda) Embedded boots (e.g. LVT) Continually supported slab (e.g. IVES)

Pre-fabricated slabs(e.g. PORR STA) Direct fastening (e.g. DFF 300 RS) Embedded rail (e.g. Edilon)

The red colour marks the elastic elements ensuring the stiffness equivalence compared to conventional ballast track.

Autodesk Rail Summit Copenhagen 2024

IVES SLAB TRACK SYSTEM

Autodesk Rail Summit Copenhagen 2024 Autodesk Rail Summit 2024

13

TYPICAL CHALLENGES OF RAILWAY OPERATORS,

ASSET MANAGERS AND DESIGN ENGINEERS

„Our clients are running more trains, so we must plan carefully to ensure a quick return to operations. “

James Cooper, Consulting Engineer

„I have not time for maintenance, but stuff keeps breaking, this is a nightmare! I need a reliable and safe track!“

Sophie Bennett, Track Engineer

*profile pictures & names are AI generatedAutodesk Rail Summit Copenhagen 2024Autodesk Rail Summit 2024

14

«As easy as constructing with LEGO!» ─ Hermann Granig (foreman, 20 yrs experience)

about the works at Zierenberg Tunnel (GER)

Autodesk Rail Summit Copenhagen 2024 Autodesk Rail Summit 2024

15Autodesk Rail Summit 2024

AS EASY & FAST AS CONSTRUCTING WITH LEGO BRICKS!

Cementitious:

Epoxy:

Autodesk Rail Summit Copenhagen 2024

Concrete:

Asphalt:

16Autodesk Rail Summit 2024 Autodesk Rail Summit Copenhagen 2024

17

COMBINING THE BEST OF BOTH WORLDS:

BOTTOM-UP AND TOP-DOWN APPROACH

Top-Down-Approach

General Characteristics

• High accuracy

• No corrections after casting

• Replacement challenging

• Big, heavy slabs

• In-situ concrete logistics & curing

time

Bottom-Up-Approach

General Characteristics

• Fast installation

• Pre-cast elements with

easy to handle dimensions

• Geometrical corrections

possible

• Easy replacement

of components

Examples

Rheda, LVT, PORR STA

Examples

ATD, Getrac

Autodesk Rail Summit Copenhagen 2024 Autodesk Rail Summit 2024

18

IVES CONSTRUCTION PROCESS: ASPHALT LAYER

High-performance wheeled pavers

from road construction

Branxton Weighbridge, NSW, AUS Asfordby Tunnel, Melton RIDC, UK

Autodesk Rail Summit Copenhagen 2024 Autodesk Rail Summit 2024

19

OPTIONAL DEPENDING ON ROUTING: SHEAR DOWEL

Autodesk Rail Summit Copenhagen 2024 Autodesk Rail Summit 2024

20

IVES CONSTRUCTION PROCESS: PLACING OF IVES ELEMENTS

Zierenberg Tunnel, GER

Autodesk Rail Summit Copenhagen 2024 Autodesk Rail Summit 2024

21Autodesk Rail Summit 2024

IVES CONSTRUCTION PROCESS: PLACING OF DFF

Bruggwald Tunnel, SWI

22

IVES CONSTRUCTION PROCESS: ASSEMBLY OF TRACK PANEL

Autodesk Rail Summit 2024

Bruggwald Tunnel, SWI

23

IVES CONSTRUCTION PROCESS: TRACK ALIGNMENT

Autodesk Rail Summit 2024

CPH Metro, DK

24Autodesk Rail Summit 2024

TRACK ADJUSTMENT SYSTEM: RHOFAS

(FINE ADJUSTMENT SYSTEM)

25

IVES CONSTRUCTION PROCESS: CASTING OF DFF 300 RS

Autodesk Rail Summit 2024

Bruggwald Tunnel, SWI

26Autodesk Rail Summit 2024

IVES CONSTRUCTION PROCESS: FIXATION SYSTEM

VFS DFF 300 RS (Rhomberg Sersa)

grout

27Autodesk Rail Summit 2024

DIFFERENT CROSS-SECTION DESIGNS AVAILABLE

embankment

tunnel invert

28Autodesk Rail Summit 2024

HOW TO TRANSITION FROM SLAB TRACK TO BALLASTED TRACK

V-TRAS VERSATILE TRANSITION MODULE

Elastic pad (blue)

Standard sleepers

(on elastic pads)

Slab track

fix point bearing

for V-TRAS

V-TRAS module

(pre-fabricated steel structure)

Elastoplastic

pad (under steel structure)

29Autodesk Rail Summit 2024

HOW TO TRANSITION FROM SLAB TRACK TO BALLASTED TRACK

V-TRAS VERSATILE TRANSITION MODULE

30Autodesk Rail Summit 2024

AFTER CONSTRUCTION AFTER A PERIOD OF USE

with V-TRAS

Standard Transition

HOW TO TRANSITION FROM SLAB TRACK TO BALLASTED TRACK

V-TRAS VERSATILE TRANSITION MODULE

AFTER CONSTRUCTION AFTER A PERIOD OF USE

GREAT DESIGN…

…BUT DOES IT WORK IN REAL LIFE?

Autodesk Rail Summit 2024

32Autodesk Rail Summit 2024

LONG TERM EXPERIENCE: BRANXTON WEIGHBRIDGE (ARTC, AUS)

▪ installed 2017

▪ epoxy grout: fast curing

▪ 120 MGT p.a.

▪ Total tonnage to date:

800 MGT

800 MGT = 40* years

20 MGT/year

*equivalent operating time in a typical European

mainline track

33Autodesk Rail Summit 2024

LONG TERM EXPERIENCE: ZIERENBERG TUNNEL (GERMANY)

General approval

for network of DB

InfraGO is pending!

Track inspection 11/2023:

no anomalies found!

“HE WHO STOPS BEING BETTER STOPS BEING GOOD.” — attributed to Oliver Cromwell

Autodesk Rail Summit 2024

35Autodesk Rail Summit 2024

PLACEHOLDER FOR ANIMATION VIDEO

36Autodesk Rail Summit 2024

ADDED VALUE OF IVES SLAB TRACK SYSTEM

MAKE THE FUTURE OF RAIL

Stefan Vonbun

Head of Superstructure Products stefan.vonbun@rsrg.com +43 664 629 69 97

Mariusz Kalinowski

Business Development Manager mariusz.kalinowski@rsrg.com +45 31 63 65 10

Folie 1: Innovative slab track solutions Folie 2 Folie 3 Folie 4 Folie 5 Folie 6: SLAB TRACK DEVELOPMENTS 60 yEArs of INVENTIONs to increase availability and reduce maintenance Folie 7 Folie 8 Folie 9 Folie 10 Folie 11 Folie 12 Folie 13: TYPICAL Challenges of railway operators, asset managers and design engineers Folie 14 Folie 15: As easy & fast as constructing with lego bricks! Folie 16 Folie 17: Combining the best of both worlds: bottom-up and top-down approach Folie 18: IVES construction process: asphalt layer Folie 19: optional depending on routing: shear dowel Folie 20: IVES construction process: placing of ives elements Folie 21: IVES construction process: placing of dff Folie 22: IVES construction process: assembly of track panel Folie 23: IVES construction process: track alignment Folie 24: Track adjustment system: rhofas (fine adjustment System) Folie 25: IVES construction process: casting of DFF 300 RS Folie 26: IVES construction process: fixation system Folie 27: different cross-section designs available Folie 28: How to transition from slab track to ballasted track v-tras versatile transition module Folie 29: How to transition from slab track to ballasted track v-tras versatile transition module Folie 30 Folie 31 Folie 32: LONG TERM EXPERIENCE: Branxton weighbridge (ARTC, AUS) Folie 33: LONG TERM EXPERIENCE: Zierenberg tunnel (Germany) Folie 34 Folie 35: Placeholder for animation video Folie 36: Added value of ives slab track system Folie 37