Parramatta Light Rail Project: transition of data from Digital Models to the Asset Management System | Presentation

Parramatta Light Rail Project: transition of data from Digital Models to the Asset Management System | Presentation

Download the full presentation now.

Parramatta Light Rail Project: transition of data from Digital Models to the Asset Management System | Presentation

© 2024 Autodesk. All rights reserved.

Rail Summit 2024 Make the Future of Rail

MAKE THE FUTURE OF RAIL

© 2024 Autodesk. All rights reserved.

Parramatta Light Rail Project (Australia)

Data from Digital Models to the Asset Management System

RA IL SUMMI T 20 24

Speakers

Architect from Madrid, ETSAM (UPM) University, with 15 years of experience in BIM

environments, being responsible for implementations in companies and BIM Manager Strategy in multidisciplinary large-scale projects. Member of the BIM User Group of Euskadi-Navarra, contributes to the standardization of this methodology in Spain.

Head of Digital BIM&CAD Area at CAF Turnkey & EngineeringEva Hernán

Architect from CEU San Pablo University with 10 years of experience in BIM environments,

being responsible for BIM coordination in different multidisciplinary projects. Currently working as BIM Engineer on coordination and management of several large-scale railway projects at CAF Turnkey & Engineering.

BIM Engineer at CAF Turnkey & EngineeringMarta Giménez

Asset & Digital Engineering Manager at CAFJulian O’Neill Digital Engineering Lead, seconded from BWB Consulting (a CAF Group Company).

11 years professional experience, in the UK and Australia in Flood Risk and Drainage Desing, with 6 years as Digital Engineering Lead on Parramatta Light Rail.

Agenda

1 Digital Engineering (DE) Strategy in Integrated Projects

2 Parramatta Light Rail (PLR) Project Overview

3 PLR DE/BIM Data Implementation Strategy

4 Modelling with Data: Overhead wiring

5 Data transition from Design&Construction to the MMIS

6 Q&A

RA IL SUMMI T 20 24

1 Digital Engineering (DE) Strategy in Integrated Projects

RA IL SUMMI T 20 24

1 Digital Engineering (DE) Strategy in Integrated Projects

CAFTE DE MMNT

PS

OCS

COMMS

CW

CDE

PCOTRA

INT

CAF GROUP

ROLLING

STOCK

DEPOT EQUIPMENT

SIG

PARTNER

RW

SUBSYSTEMS

CIVIL WORKS

CAF DE MANAGEMENT

CDE PCOINTEGRATION

INTEGRATED DE MANAGEMENT

CDE PCOINTEGRATION

Design Construction As Built O&Manteinance

Integrated

Project

CAF Project

Conventional

Project

RA IL SUMMI T 20 24

1 Digital Engineering (DE) Strategy in Integrated Projects

CLEAR OBJECTIVES

+

PROCESS SIMPLIFICATION

REDUCTION OF EFFORTS

+

INCREASE OF QUALITY

=

2 Parramatta Light Rail (PLR) Project Overview

12 km

16 Stops

2 Wire sections

13 CAF Urbos 100

RA IL SUMMI T 20 24

Federated Model

2 Parramatta Light Rail (PLR) Project Overview

RA IL SUMMI T 20 24

OIR + AIR + PIR + EIR = PDCS

PAS

1192-2

UCS

AIS

CDE PIM AIM GIS

BIM/CAD/GIS

2D 3D 4D

DEXP

MPDT

LOD

LOI770 Users

22 Companies

12 Disciplines

130 Subdisciplines

383 Models

30000 Assets

3 PLR DE/BIM Data Implementation Strategy

Autodesk SW

7000 Maintained Assets

RA IL SUMMI T 20 24

OIR + AIR + PIR + EIR = PDCS

PAS

1192-2

UCS

AIS

CDE PIM AIM GIS

BIM/CAD/GIS

2D 3D 4D

BEP

MPDT

LOD

LOI

Easy info

Essential Modelling +

Updated Teams

= PDCS

PAS

1192-2

UCS

AIS

CDE PIM AIM GIS

BIM/CAD/GIS

2D 3D 4D

DEXP

MPDT

LOD

LOI

Unique data base

Coordinated data

Updated Client

Unified Data

Simple Models +

Easy workflows

DEXP:

GIS Protocol

Asset Register

Information Protocol

770 Users

22 Companies

12 Disciplines

130 Subdisciplines

383 Models

30000 Assets

3 PLR DE/BIM Data Implementation Strategy

=

Autodesk SWAutodesk SW

7000 Maintained Assets

RA IL SUMMI T 20 24

DEXP:

Asset Register

Information Protocol

3 PLR DE/BIM Data Implementation Strategy

RA IL SUMMI T 20 24

TECHNICAL DESIGN Required

Technical DATA

3

SUBSYSTEMS Asset

Register WIP

Project Asset Register

Digital Engineering Deliverables

CDE

PLR DE/BIM Data Implementation Strategy

Asset Register

Information Protocol

PDCS (Client)

DEPX & Protocols

RA IL SUMMI T 20 24

SYSTEM

OS-ALL System – Overhead Structures – Project Wide

SYSTEM

OS-L10 System – Overhead Structures – L10 Corridor (WMD > PMS)

POSITION

OS-OHWS-CME-CP2+223 POSITION – Overhead Wiring Structure – CUMBERLAND HOSPITAL - CP2+223

Overhead Wiring Pole – Anchor Pole - SSA

SYSTEM

OS-OHWS-L10 System – Overhead Structures – Wiring – L10 Corridor (WMD > PMS)

ASSET

CP2+223-FT ASSET – Overhead Wiring Structure – CUMBERLAND HOSPITAL - CP2+223 - Footing

ASSET

CP2+223-PL ASSET – Overhead Wiring Structure – CUMBERLAND HOSPITAL - CP2+223 – Pole

CV06100100

ASSET

CP2+223-AN ASSET – Overhead Wiring Structure – CUMBERLAND HOSPITAL - CP2+223 - Anchor

ASSET

CP2+223-BC ASSET – Overhead Wiring Structure – CUMBERLAND HOSPITAL - CP2+223 – Bonding Connection

ASSET

CP2+223-BP ASSET – Overhead Wiring Structure – CUMBERLAND HOSPITAL - CP2+223 – Bonding Pit

3 PLR DE/BIM Data Implementation Strategy

Asset Register

Information Protocol STRUCTURE & CONTENT → MODELS & ASSETS

Supply Contractor (CAF) INFRA CONTRACTOR

C O

M P

A N

Y A

C O

M P

A N

Y B

FEDERATED MODEL

C O

M P

A N

Y A

C O

M P

A N

Y A

C O

M P

A N

Y A

RA IL SUMMI T 20 24

TECHNICAL DESIGN

Overhead Design Software DATA

Other Technical DATA

+

4 Modelling with Data: Overhead wiring

Overhead Asset

Register WIP

Project Asset Register

DATA IMPLEMENTATION

DYNAMO SCRIPTS FOR DATA TRANSFER

MODELS FOR COORDINATION & DELIVERY2D DRAWINGS

RA IL SUMMI T 20 24

4 Modelling with Data: Overhead wiring

PROJECT CREATIONSIMULATION DATARESULTSDATA CHECKDATA EXTRACTION

RA IL SUMMI T 20 24

4 Modelling with Data: Overhead wiring

RA IL SUMMI T 20 24

4 Modelling with Data: Overhead wiring

RA IL SUMMI T 20 24

SUBSYSTEMS Asset

Register WIP

Project Asset Register

IFC Model

CDE

Asset Register

Information Protocol

MMIS Asset

Information System – Hexagon

EAM

5 Data transition from Design&Construction to AIS

Project Asset Register

RA IL SUMMI T 20 24

5 Data transition from Design&Construction to MMIS

Using BIM in HxGN EAM

RA IL SUMMI T 20 24

Using BIM in HxGN

5 Data transition from Design&Construction to MMIS

Project Asset Register

RA IL SUMMI T 20 24Model view Real view

RA IL SUMMI T 20 24Model view Real view

¿Q&A?

Thank you!

Data from Digital Models to the Asset Management System

www.cafte.com

Eva Hernán eva.hernan@cafte.com

Julian O‘Neill julian.oneill@caf.net

Marta Giménez marta.gimenez@cafte.com

mailto:eva.hernan@cafte.com mailto:eva.hernan@cafte.com

Rail Summit 2024 Presentation Folie 1: Rail Summit 2024 Folie 2: Data from Digital Models to the Asset Management System Folie 3: Speakers Folie 4: Agenda Folie 5 Folie 6 Folie 7 Folie 8 Folie 9 Folie 10 Folie 11 Folie 12 Folie 13 Folie 14 Folie 15 Folie 16 Folie 17 Folie 18 Folie 19 Folie 20 Folie 21 Folie 22 Folie 23 Folie 24: ¿Q&A? Folie 25: Thank you!


Item Type: pdf