Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works | Presentation
Download the full presentation now.

MAKE THE FUTURE OF RAIL
© 2024 Autodesk. All rights reserved.
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
1 INTRODUCTION
2 GEOLOGICAL CHARACTERIZATION
BASED ON MODELS 2.1 Introduction 2.2 Reasons
2.3 Information 2.4 Transformation
2.5 Geolog ical model
3 GEOLOGICAL MODEL UPDATE
3.1 Continuos improvement
5 MODEL-BASED DESIGN (C&C)
5.1 Design criteria 5.2 Modeling criteria 5.3 Workflow
7 CONCLUSIONS
4 MODEL-BASED DESIGN & CONSTRUCTION
4.1 Ground Treatments 4.2 Tunnels & Caverns
6 MODEL-BASED CONSTRUCTION (C&C)
6.1 Workflow overview 6.2 Diaphragm walls
6.3 Sheet pi les
1 INTRODUCTION
2 GEOLOGICAL CHARACTERIZATION
BASED ON MODELS 2.1 Introduction 2.2 Reasons
2.3 Information 2.4 Transformation
2.5 Geolog ical model
3 GEOLOGICAL MODEL UPDATE
3.1 Continuos improvement
5 MODEL-BASED DESIGN (C&C)
5.1 Design criteria 5.2 Modeling criteria 5.3 Workflow
7 CONCLUSIONS
4 MODEL-BASED DESIGN & CONSTRUCTION
4.1 Ground Treatments 4.2 Tunnels & Caverns
6 MODEL-BASED CONSTRUCTION (C&C)
6.1 Workflow overview 6.2 Diaphragm walls
6.3 Sheet pi les
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
• The Sandbukta-Moss-Såstad (SMS) Project is
part of the nacional plan called “Intercity”
Introduction The project
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
• The Sandbukta-Moss-Såstad (SMS) Project is
part of the nacional plan called “Intercity”
• Main stakeholder’s
OWNER
DESIGNERS
CONTRACTOR
CONTRACT TYPE E P C
Introduction Stakeholder’s
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
• The Sandbukta-Moss-Såstad (SMS) Project is
part of the nacional plan called “Intercity”
• Main stakeholder’s
• Main characteristics
2019 - 2025
10,3 km of double-track railway
4450 m in 2 railway tunnels
2350 m in tunnel adits, galleries and caverns
1340 m in 3 Cut & Covers
Introduction Characteristics
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Characterization
Geology & Geotechnics
baseline and updates based
on real site data.
Design
Underground Works, tunnel
portal structures, retaining
structures and ground
treatments.
Construction Support
Construction supporting
activities throughout site
works execution.
Carlberg Cut & Cover Larkovayen Cut & CoverGeological model Moss Tunnel
2300m Moss Tunnel
2150m Carlberg Tunnel
2350m Galleries & Caverns
450m C&C Kransen
490m C&C Carlberg
400m C&C Larkovayen
ACCIONA Engineering
Introduction ACCIONA Engineering’s Scope of Works
1 INTRODUCTION
2 GEOLOGICAL CHARACTERIZATION
BASED ON MODELS 2.1 Introduction 2.2 Reasons
2.3 Information 2.4 Transformation
2.5 Geolog ical model
5 MODEL-BASED DESIGN (C&C)
5.1 Design criteria 5.2 Modeling criteria 5.3 Workflow
7 CONCLUSIONS
4 MODEL-BASED DESIGN & CONSTRUCTION
4.1 Ground Treatments 4.2 Tunnels & Caverns
6 MODEL-BASED CONSTRUCTION (C&C)
6.1 Workflow overview 6.2 Diaphragm walls
6.3 Sheet pi les
3 GEOLOGICAL MODEL UPDATE
3.1 Continuos improvement
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
Geological characterization based on models Introduction
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
D e s i g n o f p r o j ec t
c r i t i c a l z o ne s
H u ge v o l u m e o f d a t a
G eo l og i c a l m od e l n o t
a r e qu i r e m en t , b u t …
Geotechnical profile of the Circle K area indicating
lower cover and posible soil composition in the
area
Large quantity and variety of documentation types
Geological characterization based on models Reasons
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
D e s i g n o f p r o j ec t
c r i t i c a l z o ne s
C o r r ec t i v e M ea s u r es
P r o p os a l : m i t i g a t i on
a nd r e m e d i a t i o n
C o ns t ru c t i on c h a l l e n ge s :
b e a d a p t a t i v e t o t h e
r e a l g eo l og y
H u ge v o l u m e o f d a t a
G eo l og i c a l m od e l n o t
a r e qu i r e m en t s , b u t …
Information from construction sources such as Jumbo Data including MWDs, laser scans, etc.
Chimney in a Project location and incident resolution
Geological characterization based on models Reasons
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
Local databases
Faults and other geological events
Sediment Geology and Hydrogeology
Previous investigations
Geological profiles
Geophysical testing and non-destructive testing
(total sounding)
In-situ and laboratory investigations
Site investigations and
geomechanical stake-outs
Geological characterization based on models Information
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
G E O M E T R I C TR A N S F OR M A T I O NG E O L O G I C A L B O R E H OL E S
Example of Borehole KBV-1 information provided to the project. Representation of the geological boreholes using the Geotechincal
module from C3D including borehole KBV-1
Geological characterization based on models Transformation
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
W E L L S I N V E S T I GA T IO N S ( N GU , N G I )
Studies conducted by NGU (Norway geologiske undersøkelse/
Geological Survey of Norway) based on existing well in the area Representation of the existing wells investigations using the
Geotechincal module from C3D
G E O M E TR I C T R A N S F O R M A TI O N
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
Geological characterization based on models Transformation
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
E R T s G E O M E TR I C T R A N S F O R M A TI O N
Información ERTs (electrical resistivity profiles). Geometric representation of the ERTs, to support the global interpretation of the
geological model.
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
Geological characterization based on models Transformation
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
W E A K N E S S Z ON E S - F A U L T S
Pland and Profiles of Weakness zones, local databases…, for
interpretation and model development 3D representation of the geometry of weakness zones (including geo-interpretations for
the 3D geoemtrical modelling).
G E O M E TR I C T R A N S F O R M A TI O N
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
Geological characterization based on models Transformation
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Transformation of the available rock data into a Civil 3D surface object for Rock surface modeling
R O C K S U R F A C E
Transformation of the topographical data into a Civil 3D surface object for
Terrain surface modeling
T O P O G R A H P I C TE R R A I N S U R F A C E
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
Geological characterization based on models Transformation
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Geological characterization based on models Geological Model
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Example of additional site
investigations campaings
designed through and
executed thorughout the
geological model
Geotechnical longitudinal
profiles extracted from the
model and inally drafted in 2D
Geological characterization based on models Geological Model
GEOLOGICAL MODELTRANSFORMATIONINFORMATIONREASONS
1 INTRODUCTION
2 GEOLOGICAL CHARACTERIZATION
BASED ON MODELS 2.1 Introduction 2.2 Reasons
2.3 Information 2.4 Transformation
2.5 Geolog ical model
3 GEOLOGICAL MODEL UPDATE
3.1 Continuos improvement
5 MODEL-BASED DESIGN (C&C)
5.1 Design criteria 5.2 Modeling criteria 5.3 Workflow
7 CONCLUSIONS
4 MODEL-BASED DESIGN & CONSTRUCTION
4.1 Ground Treatments 4.2 Tunnels & Caverns
6 MODEL-BASED CONSTRUCTION (C&C)
6.1 Workflow overview 6.2 Diaphragm walls
6.3 Sheet pi les
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Baseline Geological Model
• Local databases
• Previous investigations • Preliminar characterization
Geological Model Update According to Project Progress
• In-situ investigations
• Complementary site campaings • Weakness zones updates
• Singular areas update
• Terrain update • Rock update
Model-based Geological progress Continuos update with site data
1 INTRODUCTION
2 GEOLOGICAL CHARACTERIZATION
BASED ON MODELS 2.1 Introduction 2.2 Reasons
2.3 Information 2.4 Transformation
2.5 Geolog ical model
5 MODEL-BASED DESIGN (C&C)
5.1 Design criteria 5.2 Modeling criteria 5.3 Workflow
7 CONCLUSIONS
4 MODEL-BASED DESIGN & CONSTRUCTION
4.1 Ground Treatments 4.2 Tunnels & Caverns
6 MODEL-BASED CONSTRUCTION (C&C)
6.1 Workflow overview 6.2 Diaphragm walls
6.3 Sheet pi les
3 GEOLOGICAL MODEL UPDATE
3.1 Continuos improvement
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Circle K Area
Initial informaiton
• Nul or reduced rock cover
• Heterogeneous soil thicknesses
• Highly fractured zone
• Urban environment
Risks
• Potential soils affecting the excavation
• Area sensitive to settlements
• Stability and leaks problems
• Damage to buildings
Moss Tunnel Ch: 58.6-58.7
Circle K original geological information Circle K areaCircle K geotechnical profile
Model-based Design & Construction Support Ground Treatments
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Ground treatment area from surface using Jet Grouting:
• Geometrical definition Jet Grouting (model-based geometricized)
• Jet Grouting execution monitoring
Data outputs: drawings, QTO and stake-out data
Model-based Design & Construction Support Ground Treatments
Conceptual design Jet Grouting (monolithic block) Detail design Jet Grouting in columns through
Dynamo scripting = multiple design alternatives
assessed
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Ground treatment area from Surface using Jet Grouting:
• Geometrical definition Jet Grouting (model-based geometricized)
• Jet Grouting execution monitoring
Model-based Design & Construction Support Ground Treatments
Executed columns model through machinery data and
dynamo scripts
ACCIONA Engineering in-house application built upon DDBB+Forge for the Jet Grouting execution monitoringProposal of corrective measures
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Parametric design in drill & blast tunnels and caverns
Geometric definition:
Parametrization of multiple tunnel sections in accordance with Design and
Spaceproofings criterias. Mosstunnelen. Lining variations and Niches variations
Model-based Design & Construction Support Tunnels & Caverns
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Parametric design in drill & blast tunnels and caverns
Model development & software design interfacing:
Creation of Tunnel corridor, drainage networks
Model-based Design & Construction Support Tunnels & Caverns
Portal structure and escape tunnel. Interface between C3D and Revit:
- Use of BIM360 and Surface publish from C3D to Revit
- Now, we would use Data Connectors
Sandbutka tunnel portal. Tunnel interface between excavation and technical buildingsMosstunnelen tunnel. Interdisicplinary coordination
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Special tunnel shoring for reduced rock cover
Geology model baselineGeology model updated with real field data Parametric design in Dynamo for the dimensioning and positioning of shoring micropiles
Model-based Design & Construction Support Tunnels & Caverns
Site investigations Special shoring designed conditioned to real site scenariosModelshoring and micropiles updated
1 INTRODUCTION
2 GEOLOGICAL CHARACTERIZATION
BASED ON MODELS 2.1 Introduction 2.2 Reasons
2.3 Information 2.4 Transformation
2.5 Geolog ical model
5 MODEL-BASED DESIGN (C&C)
5.1 Design criteria 5.2 Modeling criteria 5.3 Workflow
7 CONCLUSIONS
4 MODEL-BASED DESIGN & CONSTRUCTION
4.1 Ground Treatments 4.2 Tunnels & Caverns
6 MODEL-BASED CONSTRUCTION (C&C)
6.1 Workflow overview 6.2 Diaphragm walls
6.3 Sheet pi les
3 GEOLOGICAL MODEL UPDATE
3.1 Continuos improvement
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Model-Based Design
Cut&Covers
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Model-Based Design (C&C) Design Criteria
• SOIL CHARACTERISTICS → QUICK CLAYS
• ROCK CHARACTERISTICS → UCS=200MPa- EXCAVATION PERFORMANCE
• RETAINEMENT SOLUTION→ DIAPHRAGM WALLS AND SHEET PILES
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Model-Based Design (C&C) Modeling Criteria
• THE CLIENT DID NOT REQUIRE MODELING OF TEMPORARY STRUCTURES
• MODEL-BASED DESIGN BENEFITS: 1. STUDY OF DESIGN ALTERNATIVES
2. ACCURACY 3. IMPROVES DECISION MAKING
4. DOCUMENTATION 5. OPTIMIZATION
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Model-Based Design (C&C) Workflow: Diaphragm Walls INPUTS
THEORETICAL ROCK LAYER DHG DIMENSIONS PERMANENT STRUCTURE
• Permanent Structure Construction Process
• Space Limitations
• Parallel Sections to Avoid Eccentric Loads
• Total Wall Length 6.40 m • 2.80 m Width DHG • 3 Cycles per Wall
• Rock & Soil Surfaces • Use of Revit Topography Links
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Model-Based Design (C&C) Workflow: Diaphragm Walls DEVELOPMENT
DYNAMO SCRIPT D-WALLS & MICROPILES PLACEMENT REBAR MODELING
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Model-Based Design (C&C) Workflow: Diaphragm Walls OUTPUTS
DESIGN DRAWINGS BENDING SCHEDULES & BoQ3D MODEL
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Model-Based Design (C&C) Workflow: Sheet Piles
THEORETICAL ROCK LAYER SHEET PILE MODEL PERMANENT STRUCTURE
DYNAMO SCRIPT SHEET PILES & MICRO PILES PLACEMENT 3D MODEL Y DRAWINGS
INPUTS
DEVELOPEMENT & OUTPUTS
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
1 INTRODUCTION
2 GEOLOGICAL CHARACTERIZATION
BASED ON MODELS 2.1 Introduction 2.2 Reasons
2.3 Information 2.4 Transformation
2.5 Geolog ical model
5 MODEL-BASED DESIGN (C&C)
5.1 Design criteria 5.2 Modeling criteria 5.3 Workflow
7 CONCLUSIONS
4 MODEL-BASED DESIGN & CONSTRUCTION
4.1 Ground Treatments 4.2 Tunnels & Caverns
6 MODEL-BASED CONSTRUCTION (C&C)
6.1 Workflow overview 6.2 Diaphragm walls
6.3 Sheet pi les
3 GEOLOGICAL MODEL UPDATE
3.1 Continuos improvement
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Construction Supporting Activities: (C&C)
D-WALLS SHEET PILESMICROPILES
ADJUSTMENTDESIGN PHASE MODEL
UPDATED MODEL CONSTRUCTION SITE DATA
Workflow overview
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Construction Supporting Activities: (C&C)
ON-SITE MEASUREMENT DEVICE MICROPILES DRILLING DATA
ROCK LAYER ESTIMATION FROM CONSTRUCTION SITE DATA
STRUCTURED DATA
Diaphragm Walls
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Construction Supporting Activities: (C&C)
MODELING SCRIPT
OUTPUTS
Diaphragm Walls
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
Construction Supporting Activities: (C&C) Sheet Piles
ADJUSTMENTDESIGN PHASE MODEL UPDATED MODEL CONSTRUCTION SITE DATA
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
1 INTRODUCTION
2 GEOLOGICAL CHARACTERIZATION
BASED ON MODELS 2.1 Introduction 2.2 Reasons
2.3 Information 2.4 Transformation
2.5 Geolog ical model
5 MODEL-BASED DESIGN (C&C)
5.1 Design criteria 5.2 Modeling criteria 5.3 Workflow
7 CONCLUSIONS
4 MODEL-BASED DESIGN & CONSTRUCTION
4.1 Ground Treatments 4.2 Tunnels & Caverns
6 MODEL-BASED CONSTRUCTION (C&C)
6.1 Workflow overview 6.2 Diaphragm walls
6.3 Sheet pi les
3 GEOLOGICAL MODEL UPDATE
3.1 Continuos improvement
Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works
MODEL-BASED CONSTRUCTION SUPPORTING ACTIVITIES:
• UPDATED MODEL FROM CONTRUCTION SITE DATA
• MODEL-BASED DECISION MAKING
• UPDATED DRAWINGS & BoQ
• ACCURATE DESIGN VALIDATION
MODEL-BASED DESIGN:
• FACILITATES THE STUDY OF DIFFERENT DESIGN ALTERNATIVES
• ENHANCED DECISION-MAKING
• DRAWINGS & BoQ LINKED TO THE MODEL
• ACCURATE DESIGN PROCESS
Conclusions
Thank you!
Digital Engineering & BIM Leader
ruben.mazarico@acciona.com
Ruben Mazarico BIM Manager
rcabezas@acciona.com
Rafael Cabezas
ACCIONA Engineering business ACCIONA Engineering business
Q&A
Rail Summit 2024 Presentation Folie 1: Digital Engineering and BIM in the Design and Construction supporting activities for Railway Underground Works Folie 2 Folie 3 Folie 4: Introduction Folie 5: Introduction Folie 6: Introduction Folie 7: Introduction Folie 8 Folie 9: Geological characterization based on models Folie 10: Geological characterization based on models Folie 11: Geological characterization based on models Folie 12: Geological characterization based on models Folie 13: Geological characterization based on models Folie 14: Geological characterization based on models Folie 15: Geological characterization based on models Folie 16: Geological characterization based on models Folie 17: Geological characterization based on models Folie 18: Geological characterization based on models Folie 19: Geological characterization based on models Folie 20 Folie 21: Model-based Geological progress Folie 22 Folie 23: Model-based Design & Construction Support Folie 24: Model-based Design & Construction Support Folie 25: Model-based Design & Construction Support Folie 26: Model-based Design & Construction Support Folie 27: Model-based Design & Construction Support Folie 28: Model-based Design & Construction Support Folie 29 Folie 30 Folie 31: Model-Based Design (C&C) Folie 32: Model-Based Design (C&C) Folie 33: Model-Based Design (C&C) Folie 34: Model-Based Design (C&C) Folie 35: Model-Based Design (C&C) Folie 36: Model-Based Design (C&C) Folie 37 Folie 38 Folie 39 Folie 40: Construction Supporting Activities: (C&C) Folie 41: Construction Supporting Activities: (C&C) Folie 42: Construction Supporting Activities: (C&C) Folie 43: Construction Supporting Activities: (C&C) Folie 44 Folie 45 Folie 46: Conclusions Folie 47: Thank you!