Audit of OpenBIM Models (IFC) in Railway Projects for ADIF | Presentation
Download the full presentation now.

MAKE THE FUTURE OF RAIL
© 2024 Autodesk. All rights reserved.
Audit of OpenBIM Models (IFC) in Railway Projects for Adif
Jose A. Civera – Nuria Martínez
https://www.group.sener/
RA IL SUMMI T 20 24
Speaker
BIM Senior Civil Engineer with 19 years of engineering
experience, specializing in BIM Management.
Master in BIM Management with more than 7 years of experience leading BIM initiatives in large-scale projects.
Head of the Sener BIM Office and lead of BIM Management team in Sener
Wide experience in implementing BIM methodologies, both at corporate and project level.
Experience as BIM Manager in large project such as: L3
Panama Metro (Panama), Oporto Metro (Portugal) and El Cairo Monorail (Egypt).
Head of BIM Office, BIM Manager, Sener
Jose A. Civera Abad
RA IL SUMMI T 20 24
Speaker
Senior Architect with 19 years of experience in Architecture
projects and, more recently, in Infrastructure projects, specialized in BIM Management.
Extensive expertise in BIM technology, which she began using
in 2013, leading large scale projects.
Wide experience in implementing BIM methodologies, both at
corporate and project level.
Responsible for overseeing the implementation of Adif's BIM requirements in infrastructure projects. This involves dynamic
project supervision of BEP and BIM Models to ensure that all BIM standards are met consistently throughout the entire
lifecycle, and projects comply with BIM requirements.
BIM Manager, Sener
Nuria Martínez Salas
Agenda
1 Introduction to Sener
2 Introduction to Adif (Spanish Railway Infrastructure Administrator)
3 Project/Contract Description
4 Adif BIM Documentation
Framework
5 BEP Review Process
6 BIM Model Review Process
7 Conclusions and Next Steps
a Manual model auditing
Model auditing with Navisworks
Model auditing with BIMCollab
Model auditing with PowerBI
b
c
d
1. Introduction to Sener
RA IL SUMMI T 20 24
Our purpose is to transform the world
by challenging the boundaries of technology
Our vision
Sener aspires to be a global ecosystem, leader in advanced
engineering and technology, recognised for tackling the most
complex projects, inspiring people and promoting their growth.
Our mission
Sener has the mission of helping its clients with innovative
and effective solutions, with the talent of leading professionals, and always with a spirit of serving society.
RA IL SUMMI T 20 24
Backlog in
2023 (M€)
1,378 4.00083 %
Non Spanish sales Workforce
Founded in 1956, Sener ranks as the largest privately owned engineering company in Spain.
Facts and figures
RA IL SUMMI T 20 24
+ 600 people
2.500 people
300 people
+ 100 people
+ 200 people
Projects
41 countries Offices
18 countries
Global footprint
RA IL SUMMI T 20 24
Sener Group
Sener Aerospace & Defence
Sener Mobility
Sener Energy
Sener Advanced Facilities
Sener
Renewable
Investments
Zabalgarbi
Organization Chart
RA IL SUMMI T 20 24
Rail +15,000 km
Transit +1,700 km
+110 systems
Highways
Ports
Buildings
Water &
Environme nt
Airports
+20,000 km
+140 ports
+600 ports
+300 projects
+180 airports
Consultancy
& New
Technologies
+ 300 proyectos
Sener Mobility
2. Introduction to Adif
RA IL SUMMI T 20 24
Adif – Spanish Railway Infrastructure Manager
Adif is responsible for the design, construction, supervision and maintenance of the rail
network, as well as network traffic management and stations.
Introduction to Adif
https://www.adif.es
https://www.adifaltavelocidad.es
https://www.adif.es/ https://www.adifaltavelocidad.es/
RA IL SUMMI T 20 24
BIM Implementation Timeline
More details in Rail Summit 2023 session “BIM Implementation in Adif and CDE
deployment” by Javier Lozano Deputy Director for BIM and Digital Continuity in Adif
(Link to session presentation)
Introduction to Adif
https://forums.autodesk.com/t5/autodesk-rail-summit-2023/adif-bim-implementation-in-adif-and-cde-deployment/td-p/12222089
3. Project/Contract Description
RA IL SUMMI T 20 24
(Addendum BIM)
(From 2022 to 2025)
(22 BIM Projects)
Peer Review of High-Speed Rail Projects
“Servicios para la supervision dinámica de
proyectos en Adif alta velocidad en regimen
de pedido abierto”
Public tender process
Peer review of complete high speed rail
projects (i.e. civil works design, track,
stations, depots, electrification, signaling…)
Includes technical review of all disciplines
designs and BIM review
Projects developed by other design
companies, not included Sener projects
Project Description
First contract
o From 2017 to 2020
o Expected 37 projects to review (NO BIM)
Second contract:
o From 2019 to 2022
o Expected 62 projects to review (NO BIM)
Third contract:
o From 2023 to 2026
o Expected >50 BIM projects to review
Total Budget of all contracts ≈ 8M€
RA IL SUMMI T 20 24
Peer Review Team
No clear schedule for
reviews is available
Up to 4 rounds to final
approval of the project
Several review teams are
required for overlapping
reviews
Difficult to organize so
reduce the review timing
was important
Project Description
RA IL SUMMI T 20 24
Peer Review process
Project Description
Design Project:
- Reports
- Drawings
- Specifications
- BoQ
- BEP
- BIM Models
Review Report
M a
x .
3 w
e e
k s
RA IL SUMMI T 20 24
Peer Review process for BIM Deliverables
Project Description
SOFTWARE
4. Adif BIM Documentation Framework
RA IL SUMMI T 20 24
Adif BIM Documentation Framework
Refers to a set of rules, standards, and
procedures developed by Adif to
implement BIM in its railway
infrastructure projects and works.
o This framework is essential for the
STANDARDIZATION, modernization and digitalization of processes
o Its primary goal is to enhance collaboration, efficiency, and quality in the
management of Adif´s infrastructure projects.
RA IL SUMMI T 20 24
Adif BIM Documentation
Framework
RA IL SUMMI T 20 24
• The main components of the
framework include:
BIM Manuals for BIM Implementation
BIM Style Guide
Specific Guidelines for BIM Uses
Adif BIM
FRAMEWORK
BIM Manuals
for BIM implementation
Specific
Guidelines for BIM uses
BIM Style Guide
RA IL SUMMI T 20 24
Adif BIM
FRAMEWORK
Specific
Guidelines for BIM uses
BIM Style Guide
BIM Manuals
for BIM implementation
Adif BIM Framework
RA IL SUMMI T 20 24
BIM Terms BIM in
Project Phase
Introduction to
BIM
BIM in
Construction Phase
BIM Manuals
for BIM implementation
BIM Manuals
Adif BIM Framework
RA IL SUMMI T 20 24
Adif BIM
FRAMEWORK
Specific
Guidelines for BIM uses
Adif BIM Framework
BIM Style Guide
BIM Manuals
for BIM implementation
RA IL SUMMI T 20 24
BIM Style Guide
Adif BIM Framework
Adif´s BIM Style Guide includes:
A Guide to developing a BIM
Execution Plan (BEP)
A Guide for auditing a BIM Execution Plan (BEP).
Guides on Digital Project Delivery
(Guide for IFC, Object Coding standard…).
A Guide for auditing BIM Models.
Guides on the use of CDE (Common
Data Environment).
Common
Data
Environment
(CDE) Guide (GUIDE)_
CDE File
coding system
(GUIDE)_
CDE Folder
structure
CDE User
Guides
BIM roles and
responsibilities
BIM
Model
Audit
Guide
(TEMPLATE)_ BIM Model
Audit
Guide for
IFC
Guide for
digital
delivery Guide for
data
generation
and
deliveryObject
coding
standard
BIM
Execution
Plan (BEP)
Audit Guide
(TEMPLATE)_
BIM Execution
Plan (BEP)
Audit Guide
BIM Style
Guide
Guide for
BIM
Execution
Plan (BEP)
Guide to
developing a
BIM
Execution
Plan (BEP)
BEP
Annexes
Templates
(TEMPLATE)_
MIDP
(TEMPLATE)_
Shared
coordinates
model
(TEMPLATE)_
BIM Execution
Plan Template
(TEMPLATE)_
Attributes Matrix
(TEMPLATE)_
Quality control
RA IL SUMMI T 20 24
BIM Style
Guide
Guide for
BIM Execution Plan (BEP)
Guide to
developing a BIM
Execution
Plan (BEP)
BEP
Annexes Templates
(TEMPLATE)_
MIDP
(TEMPLATE)_
Attributes
Matrix
(TEMPLATE)_
Quality control
(TEMPLATE)_
Shared
coordinates
model
(TEMPLATE)_
BIM Execution
Plan Template
BIM Style Guide – Developing a BIM Execution Plan
Adif BIM Framework
The Guide to developing a BIM
Execution Plan (BEP), includes:
o Guidance explaining what is expected form the BEP
o A well-organized BEP Template
(that covers all the aspects required)
o Various templates for several of
the required BEP Annexes (MIDP, Attribute Matrix, BIM quality control
checklist…)
Content of the document is
completely standardized
RA IL SUMMI T 20 24
Guide to
developing a BIM
Execution
Plan (BEP)
(TEMPLATE)_
BIM Execution
Plan Template
BIM Style
Guide
BIM Style Guide – Developing a BIM Execution Plan
Adif BIM Framework
RA IL SUMMI T 20 24
(TEMPLATE)_
MIDP
(TEMPLATE)_
Attributes
Matrix
(TEMPLATE)_
Quality control
(TEMPLATE)_
Shared
coordinates
model
BIM Style
Guide
BEP
Annexes Templates
BIM Style Guide – Developing a BIM Execution Plan
Adif BIM Framework
RA IL SUMMI T 20 24
BIM Style
Guide
Guide for
BIM Execution Plan (BEP)
BIM
Execution Plan (BEP) Audit Guide
(TEMPLATE)_
BIM Execution
Plan (BEP) Audit
Guide
BIM Style Guide – Auditing a BIM Execution Plan
The Guide for auditing a BIM Execution Plan (BEP), includes:
o Indications of all the aspects that should be reviewed
o Template checklist for a reviewer to make sure all aspects required are audited.
This checklist is the contractual deliverable of the project and is shared with the suppliers once the BEP audit is completed.
There could be several reviews before the BEP is finally approved.
Adif BIM Framework
RA IL SUMMI T 20 24
BIM
Execution Plan (BEP) Audit Guide
(TEMPLATE)_
BIM Execution
Plan (BEP) Audit
Template
BIM Style
Guide
BIM Style Guide – Auditing a BIM Execution Plan
Adif BIM Framework
RA IL SUMMI T 20 24
Guide for IFC Guide for
digital delivery
Guide for data
generation and delivery
Object coding
standard
BIM Style
Guide
BIM Style Guide – Digital Project Delivery
Adif BIM Framework
The Guides on Digital Project
Delivery lead suppliers in relation
to different aspects:
o IFC production
o Digital delivery
o Data generation and delivery
o Object coding
RA IL SUMMI T 20 24
BIM Style
Guide Guide for IFC
Guide for data
generation and delivery
Guide for IFC Object coding
standard
BIM Style Guide – Digital Project Delivery
Adif BIM Framework
RA IL SUMMI T 20 24
BIM Style
Guide
BIM Model
Audit Guide
(TEMPLATE)_
BIM Model Audit
BIM Style Guide – Auditing BIM Models
Adif BIM Framework
The Guide for auditing a BIM Model, includes:
o Indications of all the aspects that should be reviewed
o Template checklist for a reviewer to make sure all aspects required are audited.
This checklist is the contractual deliverable of the project and is shared with the suppliers once the model audit is completed.
There could be several reviews before the BIM Model is finally approved.
RA IL SUMMI T 20 24
BIM Model
Audit Guide
(TEMPLATE)_
BIM Model Audit BIM Style
Guide
BIM Style Guide – Auditing BIM Models
Adif BIM Framework
RA IL SUMMI T 20 24
BIM Style
Guide
Common Data
Environment (CDE) Guide
(GUIDE)_
CDE File coding
system
(GUIDE)_
CDE Folder
structure
CDE User
Guides
BIM roles and
responsibilities
BIM Style Guide – Use of Common Data Environment
Adif BIM Framework
The Guides on the use of CDE
lead suppliers and reviewers on
the use of a Common Data
Environment (CDE) in different
aspects:
o File coding system
o BIM Roles and responsibilities
o CDE Folder structure
o CDE Use
RA IL SUMMI T 20 24
(GUIDE)_
CDE File coding
system
(GUIDE)_
CDE Folder
structure
CDE User
Guides
Common Data
Environment (CDE) Guide
BIM Style
Guide
BIM roles and
responsibilities BIM Style
Guide
BIM Style Guide – Use of Common Data Environment
Adif BIM Framework
RA IL SUMMI T 20 24
Adif BIM
FRAMEWORK
Adif BIM Framework
BIM Manuals
for BIM implementation
Specific
Guidelines for BIM uses
BIM Style Guide
RA IL SUMMI T 20 24
Specific
Guidelines for BIM uses
2D DRAWING
PRODUCTION
(GUIDE)_
Guide for 2D documentation
DIGITAL
MEETINGS
(GUIDE)_
Guide for digital meetings
(TEMPLATE)_
Template for digital meetings
ENGINEERING
CALCULATIONS AND ANALYSIS
COST
ESTIMATION 5D
(GUIDE)_
Guide for cost estimation 5D
CONSTRUCTION
SIMULATION (GUIDE)_
Guide for construction
progress
tracking
4D SCHEDULING /
PLANNING
(GUIDE)_
Guide for 4D scheduling /
planning
SUSTAINABILITY
AS-BUILT
(GUIDE)_
Guide for As- Built Model
3D
COORDINATION / CLASH
DETECTION(TEMPLATE)_
Template for Coordination /
Clash Detection
SITE ANALYSIS
(GUIDE)_
Site analysis guide
COMMERCIAL
VISUALIZATION
(GUIDE)_
Commercial visualization
guide (GUIDE)_
Coordination / Clash Detection
guide
Specific Guidelines for BIM Uses
Adif BIM Framework
RA IL SUMMI T 20 24
Specific
Guidelines for BIM usesSpecific Guidelines for BIM Uses
Adif BIM Framework
5. BEP Review Process
RA IL SUMMI T 20 24
The supplier elaborates the BEP
and its annexes according to
Adif´s Guide to developing a BIM
Execution Plan (BEP)
Document is reviewed against
tender requirements and Adif BIM
framework
Content of the BEP:
o BEP
o Annexes:
BEP Review Process
BIM Style
Guide
Guide for
BIM Execution Plan (BEP)
Guide to
developing a BIM
Execution
Plan (BEP)
BEP
Annexes Templates
(TEMPLATE)_
MIDP
(TEMPLATE)_
Model
Attributes/
Parameters
(TEMPLATE)_
Quality control
(TEMPLATE)_
Shared
coordinates
model
(TEMPLATE)_
BIM Execution
Plan Template
• MIDP
• BIM Project Manual
• Attributes matrix
• Model mock-up
• Export templates
• Objects classification
• File naming convention
• Clash matrix
• Models' templates
• …
RA IL SUMMI T 20 24
Guide for
BIM Execution Plan (BEP)
BIM
Execution Plan (BEP) Audit Guide
(TEMPLATE)_
BIM Execution
Plan (BEP) Audit
Guide
BIM Style
Guide
Sener audits BEP and annexes
according to Adif´s BIM Execution
Plan (BEP) Audit Guide:
o 123 items to check (+ General comments if applicable)
o Checks follow BEP content:
BEP Review Process
1. Introduction
2. BIM Objectives
and BIM Uses
3. BEP structure
4. Resources
5. BIM Strategy
6. BIM Deliverables
7. CDE
8. Quality Control
9. Standardization
10.Digital meetings
11.References
12.General comments
RA IL SUMMI T 20 24
Sener goes through the audit checklist and gives a
score: A, B, C or D, to each aspect reviewed.
BEP Review Process (TEMPLATE)_
BIM Execution
Plan (BEP) Audit
Template
Comment status:
o A = Passed, no objections
o B = There are comments that
should be attended
o C = Fail, EIR not fulfilled
o D = Not applicable
All comments must have A
status for approval
RA IL SUMMI T 20 24
Limited room for automation.
Compile typical comments of typical non-
conformities, on each item.
Share previous audit reports with the team to
coordinate the type of responses.
Coordinate with Adif the actions on several
items and situations.
Dedicated meetings with suppliers, if needed,
for clarifications.
BEP Review Process (TEMPLATE)_
BIM Execution
Plan (BEP) Audit
Template
6. Model Review Process
RA IL SUMMI T 20 24
Description of the process
The supplier elaborates the BIM Models
according to the previously approved BEP.
Sener audits BIM Models according to Adif´s
BIM Model Audit Guide and Template:
o 65 items to check: 21 critical and 44 noncritical
o Checks are grouped and a total score on each group is obtained: (Max score of each group in
brackets)
Model Review Process
BIM Style
Guide
BIM Model
Audit Guide
(TEMPLATE)_
BIM Model Audit
• 0_General Requirements (3)
• 1_Information on files (3)
• 2_Geometrical checks (2)
• 3_Information on objects (2)
• 4_Interoperability with IFC (2)
• 5_2D Drawings (2)
• 6_3D Coordination and clashes (2)
• 7_4D Simulation (2)
• 8_5D BoQ (2)
RA IL SUMMI T 20 24
Description of the process
Sener goes through the audit checklist and gives a score: Yes, No or Not Applicable, to
each item to be reviewed.
Model Review Process
Evaluation criteria:
o Critical item fails = 0 score on
that group
o More than half of noncritical fails = 0 score on that group
o Other cases = maximum score
on that group
Total score must be 20 for
approval
6. Model Review Process
Sener´s model review process has gone through an evolution of different
Maturity Levels.
1 Manual model auditing
Model auditing with Navisworks
Model auditing with BIMCollab
Model auditing with PowerBI
2
3
4
Manual model auditing1
6. Model Review Process
RA IL SUMMI T 20 24
Manual Model auditing
No specific software for auditing models is used
No automation of reviews
No systematic approach
Sampling check
Output: Excel file report
Model Review Process 1
Model auditing with Navisworks Manage2
6. Model Review Process
RA IL SUMMI T 20 24
Model auditing with Navisworks Manage
Navisworks Manage
Selection inspector.
o Select all Adif´s standard properties
that should be audited/inspected.
Model Review Process 2
RA IL SUMMI T 20 24
Model auditing with Navisworks Manage
Navisworks Manage
Selection inspector.
o Export that selection so that it can be
reused for auditing/inspecting
the same Adif´s standard properties in future projects.
Model Review Process 2
RA IL SUMMI T 20 24
Model auditing with Navisworks Manage
Navisworks Manage
Selection inspector.
o By selecting all properties in the
“Selection tree”, all the values for the
selected properties can be inspected.
Model Review Process 2
RA IL SUMMI T 20 24
Model auditing with Navisworks Manage
Navisworks Manage
Selection inspector.
o Export results of selection inspector to
CSV, to be later checked in Excel.
Model Review Process 2
RA IL SUMMI T 20 24
Model auditing with Navisworks Manage
Clash detective.
o Clashes
o Duplicates
Model Review Process 2
RA IL SUMMI T 20 24
Model auditing with Navisworks Manage
More accurate audit compared with previous process.
Navisworks configuration shared between teams but in local folders
Clash analysis is easy to obtain
Output: Excel file report + some indications about specific objects
Model Review Process 2
Model auditing with BIMcollab Zoom3
6. Model Review Process
RA IL SUMMI T 20 24
What items of the audit checklist can be automated?
3Model auditing with BIMcollab Zoom
Model Review Process
25 of 65 items can
be automated
9 critical items and
16 noncritical items
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Information aspects:
o 1A.5 - All files are in the correct software version specified in BEP
o 3.1 - All objects are correctly named following the naming convention
o 3.2 - All objects have a unique identifier
o 3.3 - All objects are correctly classified according to Railway Innovation HUB (RIH)
o 3.4 - All objects contain the required Psets
o 3.5 - All Psets contain the required attributes
o 3.6 - The Psets names are correct
o 3.7 - The type of the attributes is correct (text, number…)
o 3.8 - The information contained in the attributes is correct
o 4.1 - All objects are correctly exported to IFC, with the correct IFC entity name
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Geometry aspects:
o 2B.3 - Model is free of duplicate objects
o 2B.4 - Model is free of visual interference
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Use of BIMcollab Zoom Lists.
o Predefined lists in BIMcollab Nexus that cover one or
more aspects of Adif´s model audit template.
o These aspects relate to information and geometry.
o All lists can be used for all model audits and are available for all the review team
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Each BIMcollab Zoom List gives answer to one or more aspects of Adif´s Model Audit
Guide template:
Adif_00_Generales
o 3.4
o 3.5
o 3.6
o 3.8
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Each BIMcollab Zoom List gives answer to one or more aspects of Adif´s Model Audit
Guide template:
Adif_02_Sistema_Coord.
o 3.4
o 3.5
o 3.6
o 3.8
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Each BIMcollab Zoom List gives answer to one or more aspects of Adif´s Model Audit
Guide template:
Adif_03_Coordinacion 3D
o 3.4
o 3.5
o 3.6
o 3.8
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Each BIMcollab Zoom List gives answer to one or more aspects of Adif´s Model Audit
Guide template:
Adif_04_4D
o 3.4
o 3.5
o 3.6
o 3.8
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Each BIMcollab Zoom List gives answer to one or more aspects of Adif´s Model Audit
Guide template:
Adif_05_5D
o 3.4
o 3.5
o 3.6
o 3.8
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Each BIMcollab Zoom List gives answer to one or more aspects of Adif´s Model Audit
Guide template:
Unique identifier
o 3.2
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Each BIMcollab Zoom List gives answer to one or more aspects of Adif´s Model Audit
Guide template:
Object naming
o 3.1
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Each BIMcollab Zoom List gives answer to one or more aspects of Adif´s Model Audit
Guide template:
RIH e IFC Entities
o 2C.2
o 3.3
o 4.1
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Each BIMcollab Zoom List gives answer to one or more aspects of Adif´s Model Audit
Guide template:
Software version and IFC type export
o 1A.5
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Each BIMcollab Zoom List is exported to Excel, where values of properties are analyzed.
In order to automate this process, several Excel spreadsheets are pre-configured.
BIMcollab Lists are introduced, in these spreadsheets to compare automatically against
the correct values defined in BEP.
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Model Audit Guide – Check 2C.2, 3.3 and 4.1
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Model Audit Guide – Check 3.1 – Step 1
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Model Audit Guide – Check 3.1 – Step 2
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
Model Audit Guide – Check 3.2
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with BIMcollab Zoom
More accurate audit compared with previous process.
Standardization in all the team thanks to cloud space in BIMCollab
Additional checks automated compared with previous process
Output: Excel file report + Auxiliary info with checks on all objects
Check for all items shared with the supplier in excel format for more accurate review.
It is needed to export parameters into excel files to obtain detailed checks
Issues with IFC 4x3 properties sets and coordinates. Software not fully compatible.
Model Review Process 3
RA IL SUMMI T 20 24
Model auditing with Power BI4
6. Model Review Process
RA IL SUMMI T 20 24
Model auditing with PowerBI
Try to simplify the steps in previous process:
o IFC files are uploaded to BIMCollab Nexus
o PowerBI connects directly to BIMCollab Nexus
Model Review Process 4
RA IL SUMMI T 20 24
Model auditing with PowerBI
Different data information is loaded in
PowerBI and connected
Additionally, some external data is
loaded in the PowerBI project:
o Excel table with applicable RIH codes
o Excel table with codes for naming convention
o List of submitted files
Model Review Process 4
RA IL SUMMI T 20 24
Model auditing with PowerBI
PowerBI dashboard: Model organization
Model Review Process 4
RA IL SUMMI T 20 24
Model auditing with PowerBI
PowerBI dashboard: Objects naming
Model Review Process 4
RA IL SUMMI T 20 24
Model auditing with PowerBI
PowerBI dashboard: Objects classification (RIH)
Model Review Process 4
RA IL SUMMI T 20 24
Model auditing with PowerBI
PowerBI dashboard: Summary per file
Model Review Process 4
RA IL SUMMI T 20 24
Model auditing with PowerBI
More accurate and simple audit compared with previous process.
PowerBI file is shared in a Sharepoint folder to be used by all the team
Additional checks automated compared with previous process
Output: Excel file report + Auxiliary info with checks on all objects + Access to PowerBI
dashboard
Dashboard helps with total results and understanding of the comments
Some issues with the access to PowerBI dashboard by external users
This is used in other projects where Sener is the design supplier
Model Review Process 4
7. Conclusions and Next Steps
RA IL SUMMI T 20 24
This process works thanks to the standardization of Adif
Audit openBIM standards (IFC) simplified the standardization
Native files needs to be checked manually and only some objects (sampling check)
This standardization was key to adapt to the projects review schedule
Different review teams in different locations with same review outputs
Some issues with coordinates and parameters when opening IFC4x3 with BIMCollab
Review checklist is similar for basic design than detail design
Conclusions and Next Steps
RA IL SUMMI T 20 24
There is a clear decrease on the hours needed for each project review and better time
response
It is always worth to plan, organize, standardize and automatize. Take a breath!
More accurate review compared with a regular peer review
Future improvements:
o Automatize additional checks from the checklist and improve PowerBI
o Explore the use of IA for the review of BEP documents
o Investigate implementation of IDS (Information Delivery Specification)
o Check applicability of IFC Validation Service from BuildingSMART (https://www.buildingsmart.org/users/services/ifc-validation-service/)
Conclusions and Next Steps
DAWN OF THE PLANTE OF THE APES (20TH CENTURY FOX)
https://www.buildingsmart.org/users/services/ifc-validation-service/
Thank you!
Head of Sener BIM Office / BIM Manager
jose.civera@mobility.sener / nuria.martinez@mobility.sener
https://www.group.sener/
Jose A. Civera / Nuria Martínez
Thanks to Adif Team for allowing us to present the
project (Javier Lozano, Jesús Miguel Ortega)
Special thanks to all Sener team involved in the
Project (Carlos del Castillo, Younes Denguir, Jordi
Molla, David Torromé, Iria Torres, Sergio Vidal,
Marc Sola, Eduardo Navarro, Joao Ribeiro,
Paloma Tenorio, Josué Romero, Bibiana
Carcelero, Luis Matamala…)
Rail Summit 2024 Presentation Folie 1: Audit of OpenBIM Models (IFC) in Railway Projects for Adif Folie 2: Speaker Folie 3: Speaker Folie 4: Agenda
1 Introduction to Sener Folie 5: 1. Introduction to Sener Folie 6 Folie 7: Facts and figures Folie 8: Global footprint Folie 9: Organization Chart Folie 10: Sener Mobility
2. Introduction to Adif Folie 11: 2. Introduction to Adif Folie 12: Introduction to Adif Folie 13: Introduction to Adif
3. Project/Contract Description Folie 14: 3. Project/Contract Description Folie 15: Project Description Folie 16: Project Description Folie 17: Project Description Folie 18: Project Description
4. Adif BIM Documentation Framework Folie 19: 4. Adif BIM Documentation Framework Folie 20: Adif BIM Documentation Framework Folie 21 Folie 22: Adif BIM Framework Folie 23: Adif BIM Framework Folie 24: Adif BIM Framework Folie 25: Adif BIM Framework Folie 26: Adif BIM Framework Folie 27: Adif BIM Framework Folie 28: Adif BIM Framework Folie 29: Adif BIM Framework Folie 30: Adif BIM Framework Folie 31: Adif BIM Framework Folie 32: Adif BIM Framework Folie 33: Adif BIM Framework Folie 34: Adif BIM Framework Folie 35: Adif BIM Framework Folie 36: Adif BIM Framework Folie 37: Adif BIM Framework Folie 38: Adif BIM Framework Folie 39: Adif BIM Framework
5. BEP Review Process Folie 40: 5. BEP Review Process Folie 41: BEP Review Process Folie 42: BEP Review Process Folie 43: BEP Review Process Folie 44: BEP Review Process
6. BIM Model Review Process Folie 45: 6. Model Review Process Folie 46: Model Review Process Folie 47: Model Review Process Folie 48: 6. Model Review Process Folie 49: 6. Model Review Process Folie 50: Model Review Process Folie 51: 6. Model Review Process Folie 52: Model Review Process Folie 53: Model Review Process Folie 54: Model Review Process Folie 55: Model Review Process Folie 56: Model Review Process Folie 57: Model Review Process Folie 58: 6. Model Review Process Folie 59: Model Review Process Folie 60: Model Review Process Folie 61: Model Review Process Folie 62: Model Review Process Folie 63: Model Review Process Folie 64: Model Review Process Folie 65: Model Review Process Folie 66: Model Review Process Folie 67: Model Review Process Folie 68: Model Review Process Folie 69: Model Review Process Folie 70: Model Review Process Folie 71: Model Review Process Folie 72: Model Review Process Folie 73: Model Review Process Folie 74: Model Review Process Folie 75: Model Review Process Folie 76: Model Review Process Folie 77: Model Review Process Folie 78: 6. Model Review Process Folie 79: Model Review Process Folie 80: Model Review Process Folie 81: Model Review Process Folie 82: Model Review Process Folie 83: Model Review Process Folie 84: Model Review Process Folie 85: Model Review Process
7. Conclusions and next steps Folie 86: 7. Conclusions and Next Steps Folie 87: Conclusions and Next Steps Folie 88: Conclusions and Next Steps
8. Close Out Folie 89: Thank you!