Leveraging BIM for $3.0 Billion Deep-Level Tunnel High-Speed Rail (GTX-B) Project
Jiyoung Kim Director of BIM Technology Development, Hanul CNB
2024 Rail Summit, Copenhagen, Denmark
Table BIM Strategy of Korea
o Mandatory application of BIM in the design and construction phases
o Examples of BIM applications at each stage of the construction lifecycle
Introduction to the GTX-B Project
o Project Overview
o Full route overview
o BIM Execution Plan
o Phase-by-phase implementation of the BEP
BIM Tools and Technologies
o BIM Model Libraries
o Modeling Automation
o Drawing Automation
BIM Utilization in the GTX Project
o Shift from 2D to BIM
o BIM-based As-Built Model
o Review of Construction and As-Built Models
o Clash Detection and Equipment Optimization
o Software requirements for information exchange
o Project Management and information exchange
Conclusion
o Benefits and Impact
Speaker
• 17 years of experience as a civil structural engineer
• 6-year experienced BIM Manager in the railway sector
• Active as an author in Autodesk BIM forums, including the Dynamo forum.
• Participation in government-led infrastructure technology research and development
• Some of the software included in today’s presentation is either developed or planned by me
Director of Hanul CNB , Leader of Research & Development DPT.
Jiyoung Kim
Smart
Construction Industries
Phased mandatory application of BIM based on project scale
o 2023 : mandated for public projects valued at over 100 billion Korean Won (roughly 70 million USD).
o 2026 : Extend to 50 billion KRW (≈ 40 million USD)
o 2028 : Over 30 billion KRW (≈ 23 million USD)
BIM Strategy of Korea Mandatory application of BIM in the design and construction phases
BIM required for public projects over 30 billion KRW
BIM required for public projects over 100 billion KRW
BIM required for public projects over 50 billion KRW
From 2023
Construction of first-class facilities such as roads and railways
Construction of second-class facilities such as bridges and tunnels
Construction of third-class facilities such as buildings
From 2026 From 2028
Traditional
Construction Industries
This gradual approach helps manage the added costs of BIM by starting with large public projects.
Gradually
adopting and
mandating
BIM Strategy of Korea Examples of BIM applications at each stage of the construction lifecycle
Design Construction Maintenance
Paradigm Shift
Applied Tech- nologies
2D Design Fragmented Stage
• 4D/5D BIM Design
• Integrated Phases
• On-site Production Labor Dependency
• Modularization • Automation
& On-site Monitoring
Information Disconnection On-site Visits Subjective
• Information Feedback
• Remote Control • Scientific
Site Data Collection Using Drones
Facility Planning with Big Data
Alternative Review Using VR
Automated BIM-Based Design
Equipment Automation & Robotic Construction
Rapid Construction Using 3D Printing
On-site Monitoring Using Drones
IoT-based Site Safety Management
Preventive Maintenance with Sensors
AI-based Facility Operation
Facility Monitoring Using Drones
#supporting the development and
applications
#Implement IoT
#Safety Speed
#Significant improvements
#why they are investing in them
Introduction to GTX-B Project Overview
Project Details
o Title Great Train Express Line B (GTX-B) Construction Project
(high-speed rail network)
o Implementing Entity MOLIT, Republic of Korea
o Route / Length Songdo to Maseok, Korea / 80.08 km
o Budget $3.0 billion (approximately 4.2 trillion KRW)
o Duration 2022 to 2030
Seoul Station
Songdo
Maseok
GTX-B
#the metropolitan area, #Inhabited 20 million #30million annually
#metropolitan rail network, #under construction
Introduction to GTX-B Full route overview
#12min, #ICN Songdo
#Icn-Metr0
#N-A Pacific Tower
#3Million
#NATM 40-80
#Commercial Dt
#UnderConstruction Prj
# C3D #LOD300
Introduction to GTX-B
BIM
Alignment & Topography
Cooperation
Structural Engineering
Tunnel
Earthworks
BIM Execution Plan
Key points of the BEP
o Alignment and Topography Design Review
o Earthwork Design Review
o Structure Design Review, Drawing, Quantity Review, Clash Detection
o Tunnel Design Review, Drawing, Quantity Review
o Interdisciplinary Interface Coordination
#CDE
Introduction to GTX-B Phase-by-phase implementation of the BEP
3D Terrain/Geological Data
3D Terrain
3D Geological Layer
▶3D terrain data based on survey ▶3D geological data for Entire Route
BIM Model Automation
Parametic Modeling
Rebar Modeling (LOD350)
▶Automatic Update BIM Models When the design changes
Parameter Based on OBS
Parameter
▶Rapid modeling automation technology for accommodating design changes
OBS-based Parameters
3D Quantity / 2D Verification
BIM Model
▶3D Quantity for Structures ▶Ensuring Accuracy
Quantity
BIM Extraction / Drawing
General Drawing
▶Extraction from BIM Model for Drawings with Additional 3D Views
Structural Drawing
Cooperation
Sharing information
▶CDE Operation with Web-Based BIM for Cooperation
Construction Management
#classification
#payment milestones
#progress paid rate
BIM Tools and Technologies BIM Model Libraries
BIM Model Libraries
o Parametric BIM Model
o Development of Technology for Improving Productivity and Quality Control od Railroad Infrastructures BIM Design (2020, KRRI)
#Design Phase
#quickly building
#Tunnel Pattern
#Rock Formation
#rapidly build
#Design status
#KoreaRailroadResearchInstitute
#Digital Libraries
#Revt #SAC
BIM Tools and Technologies BIM Model Libraries
#Parametric Model
#Time required
#Design Changes
#Same Quality
BIM Tools and Technologies Linear Structures
Curved Linear Models
#3D Linear
#Curved Structures
BIM Tools and Technologies Modeling Automation
Automation of Linear Structure Modeling
#parametric tunnel
cross-section profiles
#Curve coordinates
#Civil3D
#Excel
#Parameter
# placed along the
tunnel alignment
#Sweep
BIM Tools and Technologies Modeling Automation
Automation of Linear Structure Modeling
#Cross Section
#Parametric Libraries
#Swep
#Linearity
#Revit Add-In
#Multiple
#Changes in Pattern
#A Single Engineer
#20%
#Quantities
#Parametric Information
BIM Tools and Technologies Modeling Automation Linear Repetitive Elements
#Parametric Libraries
#Sleepers
#Catenary Poles
#Along the alignment
BIM Tools and Technologies Modeling Automation
Automated Modeling
#Deatiled Information
#Parameters
#Scheduling Data
BIM Tools and Technologies Drawing Automation
Draft & Drawings
o Paperless
▶Dall E
#BIM fully implemented
#Tablet PCs
#Paper Drawings Disappear
▶Development of Technology for Improving Productivity and Quality Control of Railroad Infrastructures BIM Design (2020, KRRI)
Survey: Will the introduction of BIM eliminate the need for paper drawings at construction sites?
It won’t be necessary
It will be necessary for the time being
It will continue to be needed
#lightweight, without smart pen
#Different approach
#Quickly Create
BIM Tools and Technologies Drawing Automation
Draft & Drawings
o Drawing Automation
#Tunnel Cross-Sections
#Essentially share
#Same Parameters
#Single parametric
tunnel cross section
#generate various
tunnel profiles
BIM Tools and Technologies Drawing Automation
Draft & Drawings
o Drawing Automation
▶AutoCAD ▶Revit Cross - Section
CAD to Revit
o Paperless
BIM Tools and Technologies Drawing Automation
Draft & Drawings
o Drawing Automation
▶AutoCAD ▶Revit Cross - Section
CAD Dimension to Revit Dimension
o Paperless
BIM Tools and Technologies Drawing Automation
Draft & Drawings
o Drawing Automation
Adjusting the dimension line
BIM Tools and Technologies Drawing Automation
Draft & Drawings
o Drawing Automation
Dimension line
BIM Tools and Technologies Drawing Automation
Draft & Drawings
o Drawing Automation
#Dimension Lines
#Revit Sheet
#Adjust dimension lines
#Similar shape
#Twice
BIM Utilization in the GTX Project Shift from 2D to BIM
▶Structural drawings ▶Underground utility drawings▶Topographic map
#Design Document
#3 Billon Dollars Project
BIM Utilization in the GTX Project BIM-based As-Built Model
GTX-B Yongsan Station
GTX-B, KTX, Seoul Metro Line 1 and 4 is installed and operated. And Shinbundang DX Line is planned.
GTX-B Seoul Station
GTX-A, B, KTX, Seoul Metro Line 1, 4, Gyeongui Line and Airport Railroad EXpress(A'REX)
is installed and operated.
#Biggest Challenge
#120 years old
#Skyscrapers
#5 metro Lines Intersect
#Avoiding Interferences
#Excavating 80-40
#All facilities #Re-implemented #Station Plan Reorganized #Gathered Information #Underground Facilities #Interferences #Updated
BIM Utilization in the GTX Project Review of Construction and As-Built Models
Pedestrian Flow Verification
The pedestrian movement path was reviewed in 3D.
Equipment Operation Review
Selection of optimal operating positions and review of working radius for construction equipment.
GTX-B Yongsan Station
Operational review of backhoe (0.6㎥)
#Indoor space in detail
#Evacuation route
#Es plans Evacuation Spaces
#YS SL Complicated / Underway
#other sections
#same sized equipment /Fusion 360
BIM Utilization in the GTX Project Clash Detection and Equipment Optimization
Clash detection
Review of interference and relocation plan between temporary structures and existing underground
facilities
Equipment Operation Review
Selection of optimal operating positions and review of working radius for construction equipment.
#range of construction equipment
#identify and address potential accidents
and risks.
BIM Utilization in the GTX Project Software requirements for information exchange
BEP
o Sharing of models and information among project participants
o Process management and input cost management based on daily reports
o BIM-based transparent cost management
o Paperless Construction Site Document Management
#CDE
#simultaneously perform 4D and 5D BIM
BIM Utilization in the GTX Project Project Management and information exchange
#All Information
#Skateholders, Clients, Contractors
#Visually represented
#multile project #Simultaneously
#work force, material
Equipment, cost
# Web-Based
#Dashboard
#monitoring construction
progress and schedules
#over 40GB to be opened
#Web Browsers
#ObjectBased Information
#Daily Construction report
Social Impact
Expansion of digitalization in the Construction industry and connectivity with Other industries
Enhanced expertise among BIM-related professionals
Employment Retention Impact
Increased job satisfaction through improved work efficiency
Development of a skilled workforce with diverse technical expertise and increased workforce demand
Technical Impact
Improved accuracy in management through continuous, universal utilization of BIM data
Digital Twin implementation
Economic Impact
Time and cost savings through automated design. Enhancing overall project speed
Reduced operational costs and material savings through high-accuracy BIM model management
Conclusion Benefits and Impacts
Q&A
Thank you!
Director of BIM Technology Development, Hanul CNB
www.hanulcnb.com
Jiyoung Kim
jicaprio80@hanulcnb.com
Linked/in/jicaprio80
MAKE THE FUTURE OF RAIL
Jiyoung Kim Director of BIM Technology Development, Hanul CNB
jicaprio80@hanulcnb.com
Linked/in/jicaprio80
www.hanulcnb.com
Rail Summit 2024 Presentation Folie 1: Rail Summit 2024 Folie 2: Leveraging BIM for $3.0 Billion Deep-Level Tunnel High-Speed Rail (GTX-B) Project Folie 3: Table Folie 4: Speaker Folie 5: BIM Strategy of Korea Folie 6: BIM Strategy of Korea Folie 7: Introduction to GTX-B Folie 8: Introduction to GTX-B Folie 9 Folie 10: Introduction to GTX-B Folie 11: BIM Tools and Technologies Folie 12: BIM Tools and Technologies Folie 13: BIM Tools and Technologies Folie 14: BIM Tools and Technologies Folie 15: BIM Tools and Technologies Folie 16: BIM Tools and Technologies Folie 17: BIM Tools and Technologies Folie 18: BIM Tools and Technologies Folie 19: BIM Tools and Technologies Folie 20: BIM Tools and Technologies Folie 21: BIM Tools and Technologies Folie 22: BIM Tools and Technologies Folie 23: BIM Tools and Technologies Folie 24: BIM Tools and Technologies Folie 25: BIM Utilization in the GTX Project Folie 26: BIM Utilization in the GTX Project Folie 27: BIM Utilization in the GTX Project Folie 28: BIM Utilization in the GTX Project Folie 29: BIM Utilization in the GTX Project Folie 30: BIM Utilization in the GTX Project Folie 31: Conclusion Folie 32: Q&A Folie 33: Thank you! Folie 34