BIM Implementation Challenges and use cases in Metro Rail | Presentation
Download the full presentation now.

© 2024 Autodesk. All rights reserved.
Rail Summit 2024 Make the Future of Rail
MAKE THE FUTURE OF RAIL
© 2024 Autodesk. All rights reserved.
BIM Implementation Challenges and Use Cases In Metro Rail
Resource – Technology – Strategy
Agenda
1 Overview of Chennai Metro Rail (CMRL)
2 BIM Implementation – Challenges,
Adoption, & Steps
3 How CMRL optimized design processes
& deliverables through Autodesk?
4 How CMRL accelerated digital project
delivery through Autodesk?
Overview of Chennai Metro Rail Limited
(CMRL)
RAI L SUM MI T 2 02 4
The Government of Tamil Nadu created a Special Purpose Vehicle (SPV) scheme for implementing the
Chennai Metro Rail Project. This SPV named as “Chennai Metro Rail
Limited” was incorporated on 03.12.2007 under the Companies
Act.
The Phase I and its Extension of Chennai Metro Rail project covers
a length of 54 kms network and consists of two Corridors with total
of 41 Stations. Started Commissioned in the year 2015 and
completed in 2019.
The Chennai Metro Rail Phase II project is a significant expansion of the city's metro rail network. Once
Phase II is fully operational, the total metro rail network in Chennai will be
173 kilometers.
A total of 23 no’s of Tunnel Boring Machines (TBMs) is expected to be
used in the Phase II of CMRL Project for boring of Twin Tunnels. Which is first in any metros around the world to have 23 Nos. of TBM
simultaneously.
The Phase II of CMRL Project is the first Metro in India to be the Single Largest Metro Rail Project to be
implemented in one stretch
Overview
Chennai Metro Rail Limited
RAI L SUM MI T 2 02 4
Salient Features
Chennai Metro Rail Phase II
Corridor 3 Madhavaram to SIPCOT
45.8 kms long with 50 stations
Corridor 4 Lighthouse to Poonamallee 26 kms long with 30 stations
Corridor 5 Madhavaram to Sholinganallur
47 kms long with 48 stations
118 Kilo Meters
118 Stations 21 Multi-modal
Integrations
Project Cost – 8 Billion USD
3 Depots
RAI L SUM MI T 2 02 4
CMRL Phase 1 & 2 Map
RAI L SUM MI T 2 02 4
Coimbatore
The Coimbatore Metro, also known as Kovai Metro, is a proposed mass rapid transit system (MRTS) in Coimbatore, Tamil Nadu. It is a significant project that aims to enhance the transportation infrastructure and connectivity of the city.
The first phase of the project will focus on constructing two corridors that will connect major landmarks in the city.
Funding for the Coimbatore Metro has been secured, with the Tamil Nadu government allocating Rs 9,000 crore for the project.
CMRL Footprint in other cities
RAI L SUM MI T 2 02 4
Madurai
Madurai Metro project is a mass rapid transit system (MRTS) proposed to be built in Madurai, Tamil Nadu by Chennai Metro Rail Ltd. (CMRL).
The project’s Detailed Feasibility Report (DFR) was prepared and submitted to the Government.
The feasibility report suggested building a 31 km metro line between Thirumangalam – Othakadai with 20 stations and a train maintenance depot
CMRL Footprint in other cities
RAI L SUM MI T 2 02 4
Speaker
NC Vijay is a seasoned BIM Project Manager with 17 years of experience in civil and
structural engineering, working across India, UAE, Singapore, and the USA. Currently the Deputy General Manager at Chennai Metro Rail Limited. He holds a B.E. in Mechanical Engineering and an M.Tech in Computer Aided Design from Anna
University, Chennai. Vijay is dedicated to advancing digital technology for sustainable and resilient projects.
He has led the integration of advanced BIM technologies, optimized project workflows and delivering high-quality outcomes. Vijay excels in managing stakeholder interactions, leading BIM strategy and implementation, and driving
change management for wider BIM adoption. He also established a BIM Studio for VR and AR at Chennai Metro Rail Limited, aiming towards Digital Twin technology.
Deputy General Manager - BIM, CMRL
NC Vijay
RAI L SUM MI T 2 02 4
BIM Implementation – Challenges, Adoption,
& Steps
RAI L SUM MI T 2 02 4
in BIM Implementation
Challenges
Managing construction projects involves major challenges like cost overruns, schedule delays, communication breakdowns,
coordination issues, and resistance to new technologies, which hinder overall efficiency.
Resistance to Adopt BIM – WHY?
• Unsupportive Organizational Culture • No Client Demand • The unwillingness of all stakeholders in BIM adoption • Lack of Clear Benefits
So, Owner / Client plays an important role in the implementation of any technology but at the other side it is the responsibilities of the consultancy / contractors to use the right
tool without hesitation
RAI L SUM MI T 2 02 4
Organization level
Factors in BIM Adoption
1. 3D Software cost
•Around 50% cost higher than the 2D software (ex., AutoCAD Vs Revit) AEC collection Autodesk is covering many software
2. Design / Drawing – (Revisions / Changes)
•Most people will think that modifications will incur more time when we do the changes in the 3D model. It's all about the strategy, how and which tools are being deployed.
3. Manpower availability
•Engineers are moving towards learning and practicing the 3D software so getting the resource is not a problem
4. Transition to new technology
•Some learnings must happen among the Junior / mid-level group in the organization to adopt any new things
5. Mis Guidance
•People unaware of the BIM advantages often misguiding the top-level organization not to adopt any new technologies
“Discuss with a BIM / Technology Expert if you are looking to implement BIM or
any new Technology in your projects”
RAI L SUM MI T 2 02 4
With BIM implementation
Steps to achieve full benefits
BIM Project Manager Deployment
• To guide the process. Without a BIM PM, initiating and formulating the BIM process will lead to incomplete use of BIM.
Organisation BIM Guidelines
Discuss, Formulate the Organization BIM Guidelines and Standards.
Employer Information requirement (EIR).
Employer Information requirement (EIR) i.e., the Contract document to be created to support BIM Implementation
The full benefits of BIM can be harvested only if the implementation stage and processes of BIM comes at the right time. Without
having the proper protocol for BIM Adaptation would leads to failure.
RAI L SUM MI T 2 02 4
in BIM Implementation
Managing hurdles
To Adopt BIM or any technology over the previous one, we need to sell our idea and convince the people at our top management level
In few cases, Straight away go ahead may happen
In other cases which is 95% which can only be convinced with producing the case studies, white papers and meeting with the software provider
In Our Case, We have submitted case studies from other metros and Infra projects adopted BIM
Next Important thing we have done some exercises and shown the results and explained the benefits
RAI L SUM MI T 2 02 4
How CMRL optimized design processes & deliverables through
Autodesk?
RAI L SUM MI T 2 02 4
Project Lifecycle With Autodesk Chennai Metro Rail Limited
Plan
•Alignment & Station planning
•Concept visualization
Design
•Detail design of station building, track, & structures
•Quantity & cost estimation
•Design collaboration
Construction
•Construction sequencing
•Construction progress
Maintenance
•Asset management •Digital twin
RAI L SUM MI T 2 02 4
Planning, Design, Construction & Maintenance
Autodesk Modeling Software in CMRL project lifecycle
Alignment Plan involves balancing safety, managing traffic flow, minimizing environmental impact and social equity
Our First Phase of work starts with the Alignment planning as this is very challenging in a dense city like Chennai.
CMRL routed the alignment even in the narrow roads to cater the needs of city mobility demand.
We have 4 continuous interchange stations with double decker trackway. Both Upline and Downline will operate 4 trains at same time.
We used Infraworks and Civil 3D for the preliminary alignment and station planning
RAI L SUM MI T 2 02 4
Design in context
Planning Stage
The viaduct bridge and station rail design process is particularly interesting in Infraworks as it has a path to Revit for final design and documentation.
The images highlights the possibilities of land / building acquisition planning developed in context within Infraworks
RAI L SUM MI T 2 02 4
Design in context
Planning Stage
3D Visualization
BIM Work starts with a Idea or Hand Sketch to 3D Model Methodology
At first instance, 3D model shall be used for the visualization purpose. For Design Alternatives on quick turn around
CMRL used Autodesk software to create the 3D views for concept / Preliminary design of stations and viaducts
Planning Stage
RAI L SUM MI T 2 02 4
Design concept - 3D Visualization
Planning Stage
RAI L SUM MI T 2 02 4
Street Level
Retail Area
Concourse Cum Platform Level 1
Platform II Level 2
Platform III Level 3
At 40m below ground with Four levels of
Interchange station connection two corridors. One of the Signature station in Chennai Metro Phase 2
Thirumayilai Metro
RAI L SUM MI T 2 02 4
Karambakkam Metro
25m above the Ground
The double-decker stations will have a common concourse and two different platforms
RAI L SUM MI T 2 02 4
Detailed Design Stage
Next step we used the Autodesk Revit software for the creation of detailed design models
Models were developed for various disciplines andused for Iteration of design at various stages
we saved a lot of time while doing the design iterations because we have employed the right 3D tool like Revit
Models were used for the extraction of quantities and cost which was very useful for the construction / Execution Tender
The various discipline design models developed for stations, viaducts and tunnels as follows,
• Structural
• Architectural
• Track
• Plumbing
• Electrical
• Mechanical (Fire Fighting, Fire Alarm & SCADA / BMS)
Different Discipline design models are shown below,
RAI L SUM MI T 2 02 4
Combined Services Model Underground Station
Structure Model Architecture Model
Electrical Model
Mechanical Model
Firefighting Model
Federated Model
RAI L SUM MI T 2 02 4
Combined Services Model Elevated Station
Federated Model
RAI L SUM MI T 2 02 4
Design – Built Contractors Models
At the stage of construction, the Civil, E&M and various system wide contractors are on board.
All our system wide contracts are Design Build contracts.
Below are the discipline wise contract for one packages, (Which is 10km approx.)
•Civil, Structural, Architectural & Plumbing
•Track
•Electrical & Mechanical
•TVS & VAC
•Telecom
•Tetra
•Power Supply & Overhead Equipment
•Platform Screen Door
•Lifts & Escalator
•Automated Fare Collection
Each station consists of 15Nos. model. We have all our models developed in Autodesk Revit and we collaborated in Autodesk BIM360 as CDE
The important use of various 3D models is the Interface Coordination and Resolution
RAI L SUM MI T 2 02 4
Interdisciplinary Coordination
Clash Mitigation Clash Detection &
Resolving
Equipment’s Space Proofing
Room Signoffs
Structural Guage/KE Check
RAI L SUM MI T 2 02 4
Room wise Equipment Coordination Interface
Signalling Equipment Room Ticket Office
Station Control RoomAuxiliary Sub Station 1
Communication Equipment Room
RAI L SUM MI T 2 02 4
Clash Detection Exercise
RAI L SUM MI T 2 02 4
Autodesk Revit and Navisworks model are being used for the progress review presentation
Color coded model for the actual site progress will be reviewed
Construction Progress Model
LIGHT H OUSE
CROSS O VER
LIGHT H OUSE ST
N
Light HouseMajor Structures Construction Progress Item Total to be Contructed Constructed
Dwall for Station 206 nos 132 nos
Dwall for Entry/Exit 79 nos 39 nos
Barrette Column for Station 30 nos Not started yet
Barrette/PIC for Station 34 nos 19 Nos
Total 349 nos 190 nos
Roof Slab over Station only 11183.162 cum 1165.897 cum
15,54
3,91
8,27
72,28
LIGHT HOUSE STATION PROGRESS %
Built Up
Planned within 30 days
Planned between 30-90 days
Planned after 90 days
Autodesk Software Used:
Light House Station S071
RAI L SUM MI T 2 02 4
Construction Progress Model
Tunnel & D-Wall
RAI L SUM MI T 2 02 4
3D Rendering
Construction Animation (VDC)
Virtual Reality
Revit – Twin Motion Integration
RAI L SUM MI T 2 02 4
3D Rendering
3D Rendering at the final stage of the
project will be very useful for the FOH and
BOH finishes finalization
We have again used the Revit, Twin motion
and 3ds Max for our interior and exterior
finishes discussions
Actual materials photos were captured from
actual elements and matched it in the 3D
model to get the real look
RAI L SUM MI T 2 02 4
3D Rendering
RAI L SUM MI T 2 02 4
Finishes Finalization Stations & Depot – Exterior & Interiors
RAI L SUM MI T 2 02 4
Fire & Smoke Study
Egress simulation
Energy Analysis for IGBC / LEED
Certification
Occupational Health and Safety
– Logistics Planning
3D Revit models For Sustainability solutions
RAI L SUM MI T 2 02 4
Smoke Study
RAI L SUM MI T 2 02 4
How CMRL accelerated digital project delivery
through Autodesk?
RAI L SUM MI T 2 02 4
Connecting Construction
To Achieve BIM Level 2 standards, CMRL
adopts the BIM360 / ACC as Common Data
Environment
CMRL mainly using the following modules
from BIM360
o Document Management
o Design Collaboration
o Model Coordination
o Insights
Common Data Environment
Managing 60+ different contractors
RAI L SUM MI T 2 02 4
CMRL – Document Management Dashboard
BIM 360
RAI L SUM MI T 2 02 4
CMRL – Design Collaboration Dashboard
BIM 360
RAI L SUM MI T 2 02 4
CMRL – Model Coordination Dashboard
BIM 360
RAI L SUM MI T 2 02 4
Asset management & Digital twin
RAI L SUM MI T 2 02 4
CMRL working towards creating precise digital replicas
of its infrastructure and assets further extends to
reinforces its dedication to sustainable environmental
development
CMRL’s main objective of Facility Management is to
achieve optimal management of the asset and, its
content (equipment, spaces, furnishings, etc.).
The digital twin initiative will bring a paradigm shift in
Chennai Metro Rail operational strategy, enabling
proactive solutions and predictive maintenance to ensure
uninterrupted service quality.
Driven by a commitment to passenger satisfaction and
operational excellence, the company is poised to extend
this transformative project to all stations, further solidifying
its position as an industry leader.
Asset Management & Digital Twin
“ Focus towards collecting & maintaining STRUCTURED DATA”
RAI L SUM MI T 2 02 4
Asset Management & Digital Twin
RAI L SUM MI T 2 02 4
• Enhances Efficiency
• Improves Collaboration
• Supports better Decision-making
Building Information Modelling
• Accurate As-builts
• Building Digital Twin
From Vision to Reality
• Right Strategy -- Right Tools – Right Resource
BIM Definitely brings benefits with,
In a Nutshell…
Overall, BIM Process & associated tools
helps throughout the project lifecycle in
building the sustainable Infrastructures
Thank you!
Deputy General Manager - BIM
Vijay.nc@cmrl.in
www.chennaimetrorail.org
Vijay NC
Q&A
Default Section Folie 1: Rail Summit 2024 Folie 2: BIM Implementation Challenges and Use Cases In Metro Rail Folie 3: Agenda
Overview Folie 4: Overview of Chennai Metro Rail Limited (CMRL) Folie 5: Chennai Metro Rail Limited Folie 6: Chennai Metro Rail Phase II Folie 7: CMRL Phase 1 & 2 Map Folie 8: CMRL Footprint in other cities Folie 9: CMRL Footprint in other cities Folie 10: Speaker
BIM Implementation – Challenges, Adoption, & Steps Folie 11: BIM Implementation – Challenges, Adoption, & Steps Folie 12: Challenges Folie 13: Factors in BIM Adoption Folie 14: Steps to achieve full benefits Folie 15: Managing hurdles
How CMRL optimized design processes & deliverables through Autodesk? Folie 16: How CMRL optimized design processes & deliverables through Autodesk? Folie 17: Project Lifecycle With Autodesk Folie 18: Autodesk Modeling Software in CMRL project lifecycle Folie 19: Planning Stage Folie 20: Planning Stage Folie 21 Folie 22: Planning Stage Folie 23: Thirumayilai Metro Folie 24: Karambakkam Metro Folie 25: Detailed Design Stage Folie 26: Combined Services Model Folie 27: Combined Services Model Folie 28: Design – Built Contractors Models Folie 29: Interdisciplinary Coordination Folie 30: Room wise Equipment Coordination Interface Folie 31: Clash Detection Exercise Folie 32: Construction Progress Model Folie 33 Folie 34: Tunnel & D-Wall Folie 35: Revit – Twin Motion Integration Folie 36: 3D Rendering Folie 37: 3D Rendering Folie 38: Finishes Finalization Folie 39 Folie 40 Folie 41 Folie 42: 3D Revit models For Sustainability solutions Folie 43: Smoke Study
Accelerate digital delivery Folie 44: How CMRL accelerated digital project delivery through Autodesk? Folie 45: Common Data Environment Folie 46: BIM 360 Folie 47: BIM 360 Folie 48: BIM 360 Folie 49: Asset management & Digital twin Folie 50: Asset Management & Digital Twin Folie 51: Asset Management & Digital Twin
Summary Folie 52 Folie 53: In a Nutshell… Folie 54: Thank you! Folie 55: Q&A