Optimizing Rail Energy Project Delivery with BIM and Autodesk | Presentation
Download the full presentation now.

MAKE THE FUTURE OF RAIL
© 2024 Autodesk. All rights reserved.
Optimizing Rail Energy Project Delivery with BIM and Autodesk Construction Cloud
Agenda
Who we are “DB Energie GmbH”
Network expansion “S-Bahn Hamburg”
What is a rectifier plant?
Application of BIM using a practical example (Neuwiedenthal rectifier plant)
DB Energie GmbH a subsidiary of DB AG
€4.0 billion in revenues
in 2023
187
refuelling
stations supply trains on
non-electrified lines
5,400
stations supplied with
power, gas
and heat
20,000
trains supplied
with electrical
power every day
7,956
kilometres of company-owned traction
power network ensures a
reliable power supply
More than 2,000
employees working for more
sustainability
and efficiency
53 power plants, RFC stations and SFC
stations in use
1,833
transformer
stations ensure the right voltage
Facts and figures
Traction power Stationary energy Services
Network expansion “S-Bahn Hamburg”
Significant population growth expected in Hamburg until in
the 2030s
Expansion of local public transport system for
environmental reasons
extreme overload of the S-Bahn corridors
2018 Project start
September 2024 Official start of construction and groundbreaking ceremony
November 2024 Conclusion financing
agreement
December 2028 Introduction for the new long trains at S2
December 2029 Planned
commissioning S6 south for train table
change
More and longer trains from and to Bergedorf
at S2
New S-Bahn line S6 into the south
of Hamburg
RA IL SUMMI T 20 24
Most of the trains on the Hamburg S-
Bahn network run on direct current. This
is taken from a conductor rail installed
next to the track. The alternating current
drawn from the tractionpower grid is converted from alternating current to the
requiredAC voltage to the required DC
voltage.
Text ersetzen
(englisch)
Most of the trains on the Hamburg S-Bahn network run on direct current. This is taken from a conductor rail installed next to the track. The alternating current drawn from the traction power grid is converted in the so-called rectifier plant from AC voltage to the required DC voltage.
alternating current 25 kV/50 Hz
direct current 1,2 kV/DC
return conductor
Feeding renewable energies into
the traction current grid. The Hamburg S-Bahn is already running on 100 percent green electricity.
Rectifier plant Here the energy is converted by transformers and rectifiers into the required overhead line voltage.
Direct current 1.2 kV The converted overhead line voltage is transmitted to the conductor rail via cables.
Return conductor cable The return conductor cables ensure that the circuit is closed and the current can flow back to the source.
Lateral conductor rail The conductor rail is used to supply the trains with electrical energy by transmitting the necessary current to the traction unit via sliding contacts. It runs along the tracks and ensures a continuous power supply.
switchgear 25 kV alternating current
transformer 25 kV/0,965 kV 50 Hz
rectifier 0,965 kV 50 Hz
1,2 kV direct current voltage (0 Hz)
The current changes its direction of flow. The frequency is 50 Hz.
The direction of flow remains the same.
switchgear 1,2 kV direct current
What is a rectifier plant?
Neuwiedenthal rectifier plant Preliminary and design planning
done
Approval planning In Progress
Award of construction
contract February 2026
Planned start of construction August 2026
Planned commissioning
March 2028
Focus of this presentation
RA IL SUMMI T 20 24
How we work
CDE: Autodesk Construction Cloud
o Document filing system
o Issue Management
Regular discussions on the model (every 2 weeks)
Approval process (technical and financial) for the design planning
Additional roles:
o BIM planner
o BIM coordinator
Additional Software: Revit for model design
Detail ACC Issue management
Nr. 45 Labeling was used twice at switch
cabinet
RA IL SUMMI T 20 24
Design planning approval process: Conventional vs. BIM
Review by operator
Revision of planning
Conventional testing and approval
Testing and approval with BIM
Completed/renewed design planning
approx. 2-4 weeks,
Completed design (model)
Review by operator and project team, with VR-Glasses Revision of planning
based on defined issues
+ check operator
approx. 0-2 weeks
approx. 1 day
Average 1-2 Loops
No Loop, 1 Process
Total time approx. 3,5 weeks
Total time approx. 6 weeks
PDF/Paper
Model/ACC Model/ACC
approx. 2 weeks before date of review
Model/ACC
approx. 1,5 weeks
What we noticed, where do we have added value?
More than 100 tasks documented → Nothing gets lost!
Higher level of detail than usual already in design planning
o Earlier clarification of technical dependencies, as required for model creation
o Specialized models enable collision checks
Advantages of checking and approving design planning
Environment model
o Easier to present to people not involved in the project -> leads to greater understanding and acceptance during approval planning
Thank you
Optimizing Rail Energy Project Delivery with BIM and Autodesk Construction Cloud
teresa.tietz@deutschebahn.com,
daniel.dn.lehmann@deutschebahn.com
Teresa Tietz & Daniel Lehmann
QR-Code inside Neuwiedenthal rectifier plant
mailto:Teresa.tietz@deutschebahn.com
RA IL SUMMI T 20 24
Q&A
Vortrag Folie 1: Optimizing Rail Energy Project Delivery with BIM and Autodesk Construction Cloud Folie 2: Agenda Folie 3: DB Energie GmbH a subsidiary of DB AG Folie 4: Network expansion “S-Bahn Hamburg” Folie 5 Folie 6: Neuwiedenthal rectifier plant Folie 7: How we work Folie 8: Design planning approval process: Conventional vs. BIM Folie 9: What we noticed, where do we have added value? Folie 10: Thank you Folie 11: Q&A