Heathrow's Digital Asset Roadmap

Nigel Stroud Principal Digital Asset Data Lead Heathrow

Robert Fitzjohn Digital Integration Manager Heathrow

Classification: Internal

02/10/20242

DIGITAL ASSETS

Connected Airport 2024

Nigel Stroud

Robert Fitzjohn

Classification: Internal

02/10/20243

IT’S ALL ABOUT THE DATA

Examples of components with unique codes

Airport, Runway, Stand, Building

Building /Infrastructure level

Room, baggage hall

Electrics, Heating, ventilation

Smoke detector, FEGP, Chiller Unit

Data ModelCommon Language - Data Structure and Classification

Classification: Internal

02/10/20244

DAY 2

Classification: Internal

02/10/20245

DIGITAL PRINCIPLES

In 2021 the

Classification: Internal

02/10/20246

WHY CHANGE

Time is wasted checking information is correct as its integrated into our systems

Loosing data intelligence by simplifying as we integrate into our systems.

Information exchanges are file based, transactional and can be unsecure. e.g. emails and third party systems. The lack of best practice information management leads to a lack of trust of information.

Colleagues in operations find it difficult to locate good quality and timely data due to end of life systems and outdated processes that are unresponsive to change.

Information silos on multiple disconnected systems creates delays in decision making and obstructs collaborative working.

Time and money is wasted resurveying information due to the mismanagement of information and lack of visibility.

Safety knowledge, trends and lesson learnt are not captured and lost in different systems

Classification: Internal

02/10/20247

TRADITIONAL DELIVERY APPROACH

Lack of

trust

Project delays

from outdated

information

Information Exchange

Information Maturity

Operate and

Maintain

Loss of

Quality

Incomplete Hard to

find

Disconnected

Poor control

and visibility

Re-survey

Gap

No early

governance

of controls

Wasted time

validating

Dumb down

Information

Unused value

Supply chain

Information

Design Build Operate

Project Gateways G3 G4 G5 G6 G7 G8G2

G1

Non

conformance

Unsecure

Behaviours

Supply Chain

Third parties

Heathrow Stakeholders

Classification: Internal

02/10/20248

COLLABORATIVE DELIVERY APPROACH

Third parties

Information Exchange

Information Maturity

Operate and

Maintain

Consistent approach

Intuitive interfaces

Connected

Automating asset integration

Shared Ownership

Embodied Carbon

Safety Risk Trends

Heat Maps • Carbon • Performance • Status and Interfaces

Requirements embedded into

Contracts Digital

Rehearsals

Virtual condition

monitoring

Design Build Operate

G3 G4 G5 G6 G7 G8G2 G1

Operational Readiness

Heathrow Stakeholders

Decisions

Supply Chain

Project Gateways

Residual Safety Info

Classification: Internal

02/10/20249

PLANNING CHANGE

Asset Management

and Digital Strategies

Digital

Roadmap

Tangible Activities

Outcomes Measurable

Benefits

User Cases

Known Challenges

Classification: Internal

02/10/202410

ROADMAP DEVELOPMENT

Page 2Heathrow Digital Asset Data Strategy

Phase 1: Alignment to Heathrow Data Strategy 2023+

Process Organisation Information Technology

P1 – Strengthen asset data governance

P2 – Establish standard core digital IM

processes

P3 – Enhance asset info and data standards

Q1 – Create IM principles and behaviours

Q2 – Assess internal and supply chain digital

capability

Q3 – Design and implement awareness training programme

Q4 – Create asset management steering

group and governance

I1 – Define the key components of the master data model

I2 – Update and implement digital HAL

gateway

I5 – Embed digital asset info reqs into contracts

I6 – Review and enhance information

security model

T1 – Define enhancements to asset data systems

T3 – Develop the brief for mobile IT

solutions

T4 – Conduct SMART assets assessment

T5 – Create roadmap governance toolkit

M o

n th

s 1

– 6

Solut ion BenefitsProblem Future

Realising the full potential of data

Data Specification

Clear data

requirements

Classification: Internal

02/10/202411

INTEGRATED ROADMAP

Need

How

What

Classification: Internal

02/10/202412

ROADMAP ACTIVITIES

Classification: Internal

02/10/202413

EXPLOITING VALUE FROM DIGITAL ASSETS

Safety Risk Cost

Planning

Embodied

Carbon Digital

Rehearsals

Project

Status

Remote

inspections

Real time data

Project

Performance

Consistent

approach

Reduced

Rework

• Automating information delivery with clear processes and technology to safeguard and exploit value.

• Creating an environment where we all trust the information, allowing us to have confidence to make excellent decisions

Classification: Internal

02/10/202414

FINANCIAL VALUE TO DIGITALISATION AND INFORMATION MANAGEMENT

We recently took part in a study run by KPMG and Atkins into the Value of Information Management. A number of other clients contributed, and the final report was issues to the ‘Centre of Digital Built Britain’ who published. Click here for full report.

We used data from the Cargo Tunnel project to highlight how new information Management approaches created monetary benefits during early design.

For Heathrow benefits were identified from:

• Reduced project or programme delivery timetable

• Enabling Design for Manufacturing and Assembly

• Supply chain outperform the client’s original requirements

• Workforce health and safety including fire

• Constructability and coordination issue resolved virtually

For Heathrow, Use of IM across our capital delivery programme is

expected to unlock cost savings of some £7.40 for every £1

invested in IM.

IM Foundations are

key to enable Digital

transformation

https://www.cdbb.cam.ac.uk/files/cdbb_econ_value_of_im_report.pdf

Classification: Internal

02/10/202415

BALANCING CHANGE

Updated standards & requirements to improve quality deliverables

Dashboard reporting and analytics to manage progress against success measures.

Onboarding & training internal teams, Partner teams and making sure users understand benefits.

Stakeholder management to communicate value to key sponsors teams and respond to business needs.

Reviewed, researched and deployed our technology that responds to desired outcomes

Technology Process

People & Leadership

Stakeholder Engagement

Training & Comms

Clear Roles & Responsibilities

Software

Automation

Analytics

Standards

Governance

Guidance & Best Practice

Automated Chaos

Frustration

Alienation

Classification: Internal

02/10/202416

UPDATED INFORMATION REQUIREMENTS

Updated and revised Heathrow’s Model and

Information Management standards to better align with ISO 19650 and industry best practice.

Expanded the documentation to make sure

that information specification was aligned to Heathrow’s required outcomes.

Authored new documentation for Heathrow’s new Programmatic approach.

Expanded information planning mechanisms to manage progressive information. Models are now required at earlier gateways.

Full Suite of IM Documentation

Clear Requirements Better quality information

Classification: Internal

02/10/202417

COLLABORATION ENVIRONMENT

Classification: Internal

02/10/202418

COMMON DATA ENVIRONMENT - DATA FLOW

Classification: Internal

02/10/202419

DELIVERABLES FORECASTING

Classification: Internal

02/10/202420

HEALTH AND SAFETY RISK IN DESIGN

• Risk Captured • Located • Insights

Classification: Internal

02/10/202421

STAKEHOLDER MANAGEMENT

Classification: Internal

MANAGING POINT CLOUD DATA

Point Clouds and 360 images Uploaded into Autodesk Construction Cloud

Classification: Internal

02/10/202423

POINT CLOUD AND

360 IMAGES

Point Cloud

Measure accurately

and annotate

Pan and walk though using

the mouse

Classification: Internal

02/10/202424

TRIAL: IMPROVE ASSET INTEGRATION EFFICIENCY

The process of integrating assets has several steps, including scheduling assets from the design, installing, labelling, checking for defects, and getting approval and sign-off for handover.

Processes are manual, data is incomplete must be reworked to fit into our operational systems. Closing out projects can get delayed and cause financial penalties.

Enhancing Heathrow’s asset integration process will reduce backlogs, improve quality, streamline financial close out, and achieve right first-time delivery.

Classification: Internal

02/10/202425

TRAINING

Type Persona Roles Description

A Lite User • HAL Programme Lead • HAL Heads

This user will have an awareness of Information Management and would need to be up-to-date.

B General User • HAL Programme Manager • HAL Senior Project Manager • HAL Project Managers

This user will primarily consume information on the solution and occasionally add documents. They may be required to raise a query against a document.

C Full User • Supplier delivery roles (example, Design Manager, IM or BIM Manager)

This user will regularly view, integrate or submit documents. In addition, they will transition documents between status codes and environments. Finally, they may be required to review, validate and approve documents.

D Hand-over User

• Supplier Hand over Managers

This user will regularly view, integrate and add documents. In

addition, they will support the transition of documents between status

codes and environments to transfer to AIM.

Grouping roles by ‘Personas’ in relation to your competency needs

Bite-sized modular and on-demand Online recordings

Our training framework has been organised with Asset Information and Asset Integration and is adapted to everyone's information management competency

needs and is available to Heathrow colleagues and partners. Different roles are grouped into 'Personas', and each Persona has their own pathway of training

modules, available as on-demand online recordings. Every user will take part in the first three modules that include a general induction, standards and CDE

concepts. Thereafter, there are additional modules for General, Full and Hand-Over users.

Classification: Internal

02/10/202426

HOW CAN WE USE ALL OUR DATA

Our Solution: We are harnessing the power of Artificial Intelligence (AI) to supplant

the role of the knowledge expert. This technology empowers our team members to

pose straightforward questions in English regarding our data sources. In response, AI

provides clear answers that are interconnected with all relevant documentation.

The system grows more knowledgeable with each query, progressively refining its

responses. Essentially, AI is amassing an understanding of our data, ready to be

utilized upon request, thereby streamlining our decision-making and action-taking processes.

The Challenge: Our organization gathers a vast array of data, essential for business

decision-making yet varied in quality and structure. Traditionally, we’ve depended on

standard search engines, which often yield an overwhelming number of results, and

subsequently, on domain experts to decipher and navigate this information.

The pandemic underscored a significant loss of corporate knowledge, prompting the

need for a more intelligent, systematic approach to diminish our dependence on

human expertise.

Classification: Internal

02/10/202427

AI ‘INFORMATION SURFACING’ TRIAL

Close Calls

Prompt

Technical Standards

Lessons To be Learnt

Response

Three use cases have been identified for implementation. The AI system will process information from both structured

and unstructured documents, and will additionally incorporate data extracted from a structured database

What is the safe width for a site

walkway?

Safe walkway width is .9 M, painted

green this can be found in…..

AI AI

We have chosen an AI solution ‘BuildPrompt’ that specialises in the data from our user cases.

Colleagues from the Health & Safety, Quality, Project Management, and Delivery Partners groups are participating in the trial. They will undergo training, and their input, as well as any successes, will be recorded throughout the trial phase.

Classification: Internal

02/10/202428

TECHNICAL STANDARDS

Classification: Internal

02/10/202429

CLOSE CALLS

Classification: Internal

02/10/202430

CLOSE CALLS

Classification: Internal

02/10/202431

WHEN AND WHERE

Classification: Internal

02/10/202432

DIGITAL HEATHROW GATEWAY LIFECYCLE 32

Gateway lifecycle, automated assurance

Classification: Internal

02/10/202433

DIGITAL ASSETS – CURRENT STATE

33

Assets

Stagnating Emerging Scaling Future-Built

• Project Managers are informed and empowered to request better data/information.

• Support for all projects in data and handover process. • Clearer connection between operational phase of asset

and ownership of outcome from the capital phase. • Collaboration and communication: Training colleagues on

how to use digital tools to collaborate and communicate effectively with their colleagues, stakeholders and delivery partners.

Current

Setting our intent in Procurement Established technology that fits our purpose Upskilling HAL colleagues

• Supply chain know this is not optional. • Teams and responsibilities are established. • Operational data requirements are clear and contractually

binding. • Delivering digital asset data foundations creating complete

and quality asset data to deliver projects under budget and faster.

• Having trusted data to enable better decisions for future infrastructure investment.

• Transition away from Documentum. • Focus on 3D model file at handover in ACC. • Create a richer view of capital project data and onward

value to Heathrow. • Enable value add activities such as cost management,

carbon tracking, operate and maintain data. • Support future focus in Capital works planning and master

planning. • Moving to a new corporate GiS solution with ESRI. • Upgrading Maximo, with migration to the cloud, enabling

easier integrations. • Deploying mobile tools, intergraded with Maximo to allow a

digitally enable workforce and improved data quality being captured at source.

Classification: Internal

02/10/202434

34

Assets

DIGITAL ASSETS - TARGET STATE

Stagnating Emerging Scaling Future-Built

Connected assets & informationIM in Capital Delivery Automated project data handover & model

checking

• Automated delivery of asset data • Improve data quality in Heathrow record • Enables all downstream O&M activities. • Reduce time to clear projects to investable

asset base • Reduce costs and resources across the

value chain • Speeds up the integration of data • Removing months in handover processes

• Supporting rapid optioneering in early gateways

• Supporting delivery rehearsal, standardized asset design, automated validation of capital data, and eliminating duplicated effort leading to safe and efficient capital delivery.

• Using BIM Level 2 standards, CDE

technology and improved processes and

ways of working across the asset lifecycle

Exploiting our digital foundations to enable: • Estimating, planning & whole-life costing • Carbon tracking through design, delivery and

operations • AI surfacing intelligent information (lessons

learnt, H&S etc)

Production of a digital twin for all new assets with: • Virtual representations of potential and

actual physical assets, their processes, users, systems and devices.

• Improved insights that supports better decision making, leading to better outcomes through investment and operational maintenance.

• Unlock data to support operations, maintenance, planning and delivery of assets, systems and passenger services

• Connected by data which can be collected from a variety of sources

Classification: Internal

02/10/202435

35

Assets

DIGITAL ASSETS - FUTURE STATE

Stagnating Emerging Scaling Future-Built

Integrated Scenario Planning An integrated digital asset base Real time asset monitoring

• Predictive Maintenance Insights: Real-time monitoring would provide data on asset health, enabling predictive maintenance. Heathrow could proactively address issues, minimise downtime, and optimise resource allocation.

• Capacity Optimization: Monitoring runway, terminal, and baggage handling systems would reveal usage patterns.

• Safety Enhancements: Monitoring safety equipment (e.g., scanners, surveillance systems) would improve emergency response.

In summary, real-time asset monitoring generates insights crucial for efficient operations, safety and passenger satisfaction.

• Centralised Data focused on reduction in administrative costs related to data management and retrieval.

• Reduced Maintenance Time and Costs: optimise maintenance schedules, improved asset operation resulting in energy savings and better resource utilization.

• Optimised Interventions Planning with reductions in maintenance costs and reduces unplanned outage time.

• Forecasting future maintenance needs: accurate predictions prevent costly emergency repairs, saving on maintenance costs.

• Vital information about the built asset can be stored and accessed throughout its lifecycle and kept current.

• This information can be easily accessed and used to assist decision making and de-risk programme execution and optimise operation and maintenance processes.

• Moving away from personal knowledge and disparate data toward a system view of our airport.

• Inform our decisions throughout an asset’s life cycle, optimised costs/ improved ROI.

• Fully integrated masterplan supporting investor engagement and future planning

• Certainty of service and cost for assets

Classification: InternalGIS at Heathrow

Today at Heathrow, GIS is used in multiple applications including;

• Management of aircraft movements • Overseeing the winter operation • Airfield inspections, • Safeguarding the Aerodrome license • Issuing work permits, • Ensuring the safety of Heathrow’s Utility

network • Space Management

Heathrow has been using GIS and spatial data since the early 1990's, using specialist, bespoke software to manage its underground utility network.

ACDM HML

http://hml-standard/mcm/index.aspx?VIEW=ACDM http://hml-standard/mcm/index.aspx?VIEW=HML

Classification: Internal

Geospatial Platform

Today • Heathrow Map Live • ESRI Desktop Tools

Analysis/Analytics • ESRI Web Map for Maximo Work

Orders • 3rd Party Data access (Open source)

• ESRI Early Opportunities (ArcGIS Pro) • Scenario Modelling • Visual Statistics • Heat maps • Risk analysis • Pattern detection • Power bi integration

ESRI Enterprise Platform (Heathrow Map Live Replacement)

Q2-Q3 - 2020 • ESRI Alfred Project completion

• ESRI Platform Opportunities • Analysis/Analytical Capabilities

• Scenario Modelling • Visual Statistics • Heat maps • Risk analysis • Pattern detection • Power bi integration

• Data inputs opportunities • Heathrow Data • 3rd Party Data access

• Open source • Apple, Locus Labs

etc.

2020 • ESRI Enterprise Platform

Completed • GIS Standards Adoption Opportunities • Automated Integration

Process • Enhanced Analysis

• Advanced modelling • Sensor Technology • Tracking/Telematics • Data feeds

2022 – 2024 (Depending on Funding) • ESRI platform Integrated with

the Heathrow Insights platform

• Enhanced Decision Making through greater access to Heathrow’s Data

• One version of the truth

2022-2024?? (Depending on Funding) • Direct feeds to and from

3rd party applications for live data exchange

• One version on the truth • Application Contract

Decisions approx. 2024

Classification: Internal

ArcGIS Online – Airside Operations Grass Cutting Proof Of Concept

Grass Cutting Current Process

• CAP772 - Wildlife Hazard Management at Aerodromes auditing requirement

• Currently a three phased data collection, storage and visualisation activity • Grass Cutting field data captured with pen/paper by the Airport Transport Officers • Senior Airfield Officers manually input the captured field data into Sharepoint • Senior Airfield Officers manually input the captured field data onto an A3 paper map (Coloured in pdf)

Current Process (Minutes)

Digital ESRI Process

Total Activity Time (Hours per week)

8.5 hours 5 hours

6 weeks required to cut all grass areas (1 round)

51 hours 30 hours

Grass is cut a total of 8 rounds through out the year

408 hours 240 hours

ESRI POC Solution Time Saving in hours per year

168 hours

Classification: Internal

Heathrow’s GIS End State Vision • To deliver latest geospatial capability,

via a cloud service, to meet current and future use cases

• Generate efficiencies from reuse and consolidation geospatial project requirements

• Deliver speed to value by building upon reusable platform with company wide usability

• Entry point into Heathrow’s connected technology, systems and data

• Heathrow owned service which can provide controlled access to partners and supply chain

NEW APPROACH TO GIS – ARCGIS ONLINE

Model Office

Operations / Engineering

Use Cases

Other

Use Cases

Carbon

Use Cases

Technology – (ESRI)

People/PS (ESRI / Heathrow)

Managed Service – Heathrow

Collaborative Data Exchange

Commercial / Property

Use Cases

Asset Information – Engineering (Base

Classification: Internal

HEATHROW EXPLORER - FIRST APPLICATION OF OUR NEW SOLUTION

Space Manager Dashboard

SPACE MANAGER DASHBOARD

SPACE MANAGER AWARD

SPACE MANAGER AWARD

https://space-manager-heathrow.hub.arcgis.com/ https://vimeo.com/sevenvideoproductions/review/935776203/7bdfc63144 https://www.youtube.com/watch?v=P24AYfPAiNs

Classification: Internal

02/10/202442

MODEL INTEGRATION CHALLENGE

• Current processes of maintaining our master records are based on integrating the graphical representation

of our assets in an AutoCAD DWG format. Our new requirements utilise Revit format models to represent

our assets, we need to develop a workflow to enable the data to be integrated into a master set of models,

representing our locations across Heathrow for both 2D and 3D data sets.

• Our intention is to retain intelligence, so we reduce resurveying for new capital work and exploit the value

of the data in operational use. We need to ensure there is no data loss during integration and when we

hand back information to new capital works.

• WE NEED HELP!

Classification: Internal

Q&A

Slide 1: Heathrow's Digital Asset Roadmap Slide 2 Slide 3 Slide 4 Slide 5 Slide 6 Slide 7 Slide 8 Slide 9 Slide 10 Slide 11 Slide 12 Slide 13 Slide 14 Slide 15 Slide 16 Slide 17 Slide 18 Slide 19 Slide 20 Slide 21 Slide 22: Managing Point Cloud Data Slide 23 Slide 24 Slide 25 Slide 26 Slide 27 Slide 28 Slide 29 Slide 30 Slide 31 Slide 32 Slide 33 Slide 34 Slide 35 Slide 36 Slide 37 Slide 39 Slide 40 Slide 41 Slide 42 Slide 43 Slide 44: Q&A